To work with an exemplary organization, who are into upgrading and expansion of new projects in mechanical installations, which provides an ample chance to work for the development of myself and the company served.
Overview
20
20
years of professional experience
Work History
Manager – Projects (Section Head)
JK Cement Limited
Panna
09.2024 - Current
Erection, tracking of progress and commissioning.
Successfully completed the installation of Clinker cooler, ESP, DPC, Clinker Silo, extraction system with all safety measures and zero harm as per operation requirement.
No load and group trails of Clinker cooler, ESP with all safety interlocks along with operations team and handover.
Revival of pre and post clinkerization equipment’s in all aspects like dismantling, over hauling, testing, process interlocking, field instruments safety interlocks, clearing of unsafe conditions, pre-commissioning checks and commissioning of total plant, since the plant was in idle condition for seven years.
Complete study of Design & documentation, preparation of purchase specifications, technical evaluation, participation in technical meetings with vendors and clients/consultants, vendor document, drawing review and approvals.
Review and understand client documents (Project & Materials specifications).
Member of the corporate Safety, Health & Environment standards & procedures committee.
Installation 12 no’s Wagon loading system with total closed shed of 650mtrs length and 7.4 Km railway siding.
Modification of Raw Mill Cyclone Outlet duct to reduce the pressure drop.
Replacement of Apron Feeder with L&T make (100% reduction in breakdown with a savings of 70 Lakhs per annum).
Installation of additional hoppers two numbers with a capacity of 150 Tons each. To feed different additives consistently. (Savings achieved around 100 Lakhs per annum).
Installation of secondary crusher to meet the requirement of Raw Mill input size, (Increase in production by 15TPH to 20 TPH with a savings of 0.8 units/tons of material).
Installation of HAG 20 MKcal capacity for cement operation during shutdown. (Savings achieved increase in production by 10 to 15 TPH).
Installation of Liquid AFR firing system to PC and kiln. (Savings achieved in SHE – avg 3.9 Kcal/Kg with annual savings of 100 Lakhs per annum).
Installation of 2000 MT steel Silo.
Installed 15 TPH & 25 TPH capacity Solid AFR feeding system with storage shed, shredder, EOT grab crane and pre-processing unit with storage shed.
Installed 40 TPH capacity Solid AFR feeding system and 25 TPH pre -processing system with storage shed, EOT grab crane.
Installation of 250 TPH additive feeding circuit.
Installation of 28mtr x 320mtrs coal storage PEB shed.
Installation of 1000MT steel and 3000 MT RCC silo.
Mechanical Kiln inspection, supporting roller grinding and adjustment, adjusting and correcting the axial thrust of the kiln. Executed the above works in almost 30 cement plants in India, UAE and the Middle East.
FLSmidth & Co. is a 140 years old project and service focused engineering business with a unique global market position. This Danish conglomerate is one of the leading players and serves the cement and the mineral industry.
Diploma Engineer Trainee
Orient Cement Ltd
Devapur
01.2006 - 02.2008
Worked as a Mechanical Maintenance shift Engineer.
Shift maintaining.
Supervision in shut down jobs like handling man power, preventive & predictive maintenance and regularly monitoring all the shutdown jobs.
M/s Orient Cement is 11000 TPD, TPM & ISO Certified Company.