1. Cement Mill Bag Filter(640000 am3/hr) at The Ramco Cement Ltd, Kolaghat, WB
Done erection and commissioning supervision


2. Cement Mill Bag Filter(680000 am3/hr) at ACC Cement Ltd, Sindri, JH
Commissioning done within deadline and received appreciation from customer.


3.Coal Mill Bag Filter (400000am3/hr) at JSW BPSL, Jharsuguda, Odisha
Erection supervision and pre-commissioning


4. Raw Mill Bag Filter (690000am3/hr) at Penna Cement Ltd, Tadipatri, AP

5. Cement Mill Bag Filter(460000am3/hr) at Ultratech Cement Ltd, Patna
Bag House PLC panel commissioning


6. Cement Mill Bag Filter(350000am3/hr) at Ghorahi Cement Pvt Ltd, Nepal


7.Cement Mill Bag Filter (690000am3/hr) at Star Cement Ltd, Jalpaiguri, WB- Completed erection, commissioning and PG test

8. RMBH, CMBH, ESP at JSW Shiva Cement (4000TPD Clinker Unit)
Done Erection, commissions along with PLC panel and TR set panels
Project completed with taking responsibility individually
Received Appreciation from customer for managing site smoothly.


9. RMBH, CMBH, ESP at Wonder Cement, Nimbehra, Rajasthan (8000TPD Clinker Unit) Performed mechanical and electrical activity
Commissioning of PLC panel, Received appreciation from customer for maintaining erection quality.

Overview

6
6
years of professional experience
4
4
years of post-secondary education
1
1
Certification
3
3
Languages

Work History

Commissioning Engineer

Thermax Ltd
07.2018 - Current
  • Erection, pre-commissioning and commissioning of ESP & process Bag Filter
  • Troubleshooting of Bag filter
  • Commissioning of PLC based panels
  • Lead commissioning activities for ESP & Bag Filter in the Steel, Cement & Power sectors, ensuring timely and successful start-ups.
  • Develop and implement commissioning plans, procedures, and checklists, ensuring alignment with project specifications and client requirements.
  • Coordinate with project managers, contractors, and clients to ensure seamless communication and execution of commissioning tasks.
  • Conduct detailed testing and verification of systems to guarantee operational efficiency and safety.
  • Mentor junior engineers and technicians, fostering a collaborative and knowledgeable team environment

Education

B.Tech - Mechanical Engineering

G L Bajaj Institute of Technology and Management, Gr. Noida, UP
07.2014 - 05.2018

12th - undefined

Jesus & Mary Academy, Darbhanga

10th - undefined

Jesus & Mary Academy, Darbhanga

Skills

Team oriented and result driven

Certification

Industrial Training at SAIL, Bhilai, Chhatisgarh, 2017

Accomplishments

  • Appreciation Letter from Wonder Cement Nimbehra Rajasthan - Received appreciation for maintaining erection quality.
  • Appreciation Letter from JSW Shiva Cement Rajgangpur Odisha - Received appreciation for managing site individually
  • Appreciation Letter from Thermax - Received appreciation for completing commissioning activity of multiple site.
  • Appreciation Letter from Thermax - Appreciation letter received for on time ACC Cement, Sindri site completion.

Projectscompleted

  • Cement Mill Bag Filter(640000 am3/hr) at The Ramco Cement Ltd, Kolaghat, WB, Done erection and commissioning supervision
  • Cement Mill Bag Filter(680000 am3/hr) at ACC Cement Ltd, Sindri, JH, Commissioning done within deadline and received appreciation from customer.
  • Coal Mill Bag Filter (400000am3/hr) at JSW BPSL, Jharsuguda, Odisha, Erection supervision and pre-commissioning
  • Raw Mill Bag Filter (690000am3/hr) at Penna Cement Ltd, Tadipatri, AP
  • Cement Mill Bag Filter(460000am3/hr) at Ultratech Cement Ltd, Patna, Bag House PLC panel commissioning
  • Cement Mill Bag Filter(350000am3/hr) at Ghorahi Cement Pvt Ltd, Nepal
  • Cement Mill Bag Filter (690000am3/hr) at Star Cement Ltd, Jalpaiguri, WB, Completed erection, commissioning and PG test
  • RMBH, CMBH, ESP at JSW Shiva Cement (4000TPD Clinker Unit), Done Erection, commissiong along with PLC panel and TR set panels Project completed with taking responsibility individually Received Appreciation from customer for managing site smoothly.
  • RMBH, CMBH, ESP at Wonder Cement, Nimbehra, Rajasthan (8000TPD Clinker Unit), Performed mechanical and electrical activity Commissioning of PLC panel Received appreciation from customer for maintaining erection quality.

Timeline

Commissioning Engineer

Thermax Ltd
07.2018 - Current

B.Tech - Mechanical Engineering

G L Bajaj Institute of Technology and Management, Gr. Noida, UP
07.2014 - 05.2018

12th - undefined

Jesus & Mary Academy, Darbhanga

10th - undefined

Jesus & Mary Academy, Darbhanga
Abhishek SinghCommissioning Engineer