- VRealize Operations Manager (VROPS).
- NSX-T operations and management.
- Oversaw IT department operations and training.
- Capacity planning/deriving projects based on VROPS reports of complete environment.
- Powercli scripting to automate and work on multiple vCenters to reduce manual man hours/complete vCenter administration/Powercli scripting to analyze VM/HOST/Cluster performance.
- VXRail and Nutanix hypervisor management.
- Managing VXRail cluster upgrades / vSAN resiliency.
- Maintaining free compute and disk space in Nutanix clusters.
- End to end management of DELL/HP/Cisco chassis and RACK servers.
- Complete Datacenter management.
- Managing CRs and project requests for all changes to be made to Infra using Axis Online Project Management System and CAB meetings.
- Handling provisioning team to provision IT infra to business.
- Interacted and negotiated with vendors, outsourcers and contractors to secure products and services.
- Collaborated with other departments to help meet IT needs and properly integrate and secure systems.
- Analyzed network security and current infrastructure to assess areas in need of improvement and develop solutions.
- Reviewed and assessed architecture design, implementation, testing and deployment needs to identify project requirements and costs.
- Identified computer hardware and network system issues, performing troubleshooting techniques for remediation.
- Storage management GUI and command line execution for multiple tasks/storage LUNs assignments/SAN zoning.
Some of the key projects:
VA closure in complete VMware environment:
- Complete VA closure of ESXI hosts in Axis Bank environment.
- Scanning and finding VA points for all ESXi hosts and vCenters using Qualys tool.
- Performing IPT on ESXi hosts.
- Closed all the open points of VA and IPT (26000 Points) to create a secure environment.
- Timeline given 8 months-Completed in 5 months.
- Implemented EMC Networker virtual data domain solution
- Have implemented EMC Networker Virtual DDV in VMware infra to take file server VMs backup.
NSX-T upgrade:
- Upgraded all ESXI host (500+) NSX-T clients and manager version without single downtime.
- Completed project within 2 months.
Scrapping of VMAX10k_179 storage (300 TB) to accommodate new flash storage:
- 300 TB of space allocated across VMware (Data and Boot LUNs) and physical servers (Windows / Linux).
- Migrated all the data along with boot LUNs for physical servers to another storage.
- Overcoming all the challenges such as ESXi upgrade, SAN zoning, creating flash copies of boot LUNs as per hardware family
- Migrating VMs without causing a single downtime
- Timeline given 1 year
- Completed in 6 months
Upgrading all ESXi hosts to ESXi 6.5 and 6.7 and remove ESXi 5.5 from environment:
- Migrated all ESXi to higher version depending on hardware compatibility.
- This includes lot of activities such as installing ESXis, migrating hosts from DV switch to standard switch without any downtime.
- Scrapped all old not supported hardware and vCenter5.5.
- Timeline given 1 Year-Completed in 6 months.
Dell Open Manage Enterprise:
- Implemented DELL OME single handedly and Dell support assist enterprise.
- Now all the DELL hardware is managed through DELL OME and auto case logging through SAE.
- Manual man efforts to upgrade DELL products is completely over.
- Timeline given 3 months-Completed in 1 month.