Project management professional with track record of delivering high-impact projects in diverse environments. Adept at driving project timelines and ensuring quality outcomes through strategic planning and execution. Highly collaborative, adaptable, and committed to team success and client satisfaction.
Overview
29
29
years of professional experience
Work History
Project Manager
Reliance Industries Limited
01.2014 - 05.2024
Following major CAPEX / PIO Piling & Civil foundation jobs were executed in brown field project including co-ordination with DEC.
E O reactor (504.0 Mt), exchanger...etc... at MEG 2 plant with 600 mm Dia BCIS piles (reactor 23 and structure 21 nos)
L P stream export at PTA 1 & 2
1.2 Km shore protection work with gabion. Value-Rs 15CR. Work was completed as per tide cycle.
PTA1 Azeotropic distillation- DH column and technological structure 26 m high, IBA tank, etc.
Total nine nos substation pressurization, VCM HCL & EDC chiller.etc.
PP/ PE 2 CT – Existing six pump foundation strengthening.
Retrofitting of PTA digester to USAB (WOG technology) @ ETP plant.
Additional rosin acid line at SBR plant. Work was completed inside the operational shed including piling & Lift at SBR plant.
Valve pit at Damka plot for 48” RIL raw water line interconnection with M/S Essar line (13 x4 x4 m).
VCM incinerator with refractory work, scrubber, heater, pumps, two distribution transformers…. etc.
PTA 2 sun dyne pump CPS and other related works during peak Covid period with minimum strength.
Fire wall (9 m x 9m) between two grid transformers at 220 KV switch yard. Just completed in 22 days including piling and civil work.
MEG 1 /2/3 PCT closer scheme. Transformer (33 KV) at MEG 2.
PTA 1 RTO with skid, water seal tank, scrubber, pump, blower, etc.
HPCCU- Technology structure with scrubber (28 m high & 102 T wt.) was directly placed over foundation.
T F 1 additive tank (BP & JIO JV) with dike wall.
Cracker pre S/D :- DSS column, DMPF heater, Dimer column including piling.
During S/D :-SBR LATEX pump foundations-8 nos
PTA 2 RTO
PTA 2 substation extension (11 X 9 m).
PE 1 & 2 flare line interconnection with 22 nos trestles foundation completed in just 40 days.
PTA 2 AZEO with technological structure.
SSF pit at CCT and ACT.
MEG 2 RTO.
DIMER column, structure, pumps, spur rack.
Superannuated as a Project Manager-Minor project cell. Total experience-36 years (RIL-Hazira-29 yrs).
SR. Manager. Civil
Reliance Industries Limited
01.1995 - 12.2013
Planning and supervision of Civil construction / Modification works for equipment’s foundations, industrials buildings, tank foundations… etc., including Piling and Civil work for PH-2 projects of Hazira Complex (MEG-2, PTA-2, and Cracker plants).
Associated works along with these were:
Various foundations work including piling for petrochemical plants.
Shutdown works for PE, PP & CPP Plants.
Construction of MRS-3 substation (60 m x 23 m).
Construction of Cracker and CPP mechanical workshop.
Construction of Polymer Lab and Documentation Centre building.
FCO & DBN jobs for Polypropylene, Polyethylene & Captive Power Plant.
Construction of PE-2 swing project.
Maintenance work at different polymer plants of the petrochemical complex.
Renovation of ADMN-1 building in all respect. (Rs1.5 CR)
Maintenance and roof sheet replacement of polymer product warehouse/ General store.
Refractory maintenance work at VCM furnace, PTA TO, CKR furnace …etc.
Face-lifting of Polymer plants & buildings including fireproofing works.
Construction of 8 nos of classrooms at J.H. Ambani School.
Renovation of RND centre in totality. (Rs 1 CR)
R2B reactor (185 T) foundation for PP plant.
Worked as PSR (plant safety representative) at Hazira petrochemical plant.
Superannuated as a Project Manager-Minor project cell. Total experience-36 years (RIL-Hazira-29 yrs).
Education
B E - Civil
01.1988
Skills
Project management
Project planning
Project planning and development
Project tracking
Accomplishments
Completed the various minor projects on time amounting to INR 250 CR plus under CAPEX budget with ZERO safety incident.