With 8 years of experience in project management, I have successfully led diverse projects from inception to completion, ensuring timely delivery and alignment with organizational goals. My expertise spans in construction and manufacturing industries , where I have consistently demonstrated strong leadership, strategic planning, and problem-solving skills. I excel in stakeholder management, risk assessment, and resource optimization, leveraging agile and traditional methodologies to drive project success. My ability to communicate effectively with cross-functional teams and adapt to dynamic environments has consistently resulted in improved project outcomes and client satisfaction.

I am seeking a managerial position within an organization where I can leverage my skills to contribute to the company’s growth while advancing my professional development.

Overview

10
10
years of professional experience

Work History

Associate Manager - Project Management Office

Megha Engineering and Infrastructure Limited
2022.06 - Current
  • Project planning, tracking and controlling schedule and cost for 4 numbers national level project with implementation of 'S' curve, Earned Value and Critical Path methods.
  • Adhering to project management parameters (Scope, Time, Cost and Quality). Identifying and resolving bottlenecks which are hampering the project progress
  • Creating WBS, Scheduling the activities (Upto L-3), tracking, implementing changes and periodic review with seniors to control and monitor the planned versus actual progress.
  • Resource Management and proper allocation of resources in terms of machinery, manpower and funds requirement.
  • Assisting top management in forecast and finalization of yearly cash flow, monthly budget requirements for completion of work.
  • Analysis of Risk through Qualitative, Quantitative assessment and using 'What if' methodology to assess variance and develop strategies with management for avoidance, reduction, transfer or acceptance of risk.
  • Documentation and record keeping work related to contractual requirements
  • Identifying and analysis of delay to develop effective recovery plan
  • Assisting Contract department by providing back up documents and drafting for EOT, Claims, COS.
  • Optimizing Value Engineering to control project cost with standard engineering practices
  • Implemented MIS for reporting to top management and publishing various periodic reports for both internal and external stakeholder.
  • Conducting review meeting and kickoff meetings with clients to discuss about project progress and challenges faced.
  • Optimizing workflow processes to reduce bottlenecks and increase overall effectiveness.
  • Managing and coordinating cross-functional departments, ensuring timely completion and alignment with company objectives.
  • Preparing feasibility report, identification of gap for business expansion

Deputy Project Manager

MRG Construction
2021.10 - 2022.04

Project: Construction of four laning of Rajauli - Bakhtiyarpur Km 101+630 to Km 152+520 (Pkg. 3) of NH 20 on HAM mode in state of Bihar. (Project Cost- 1200 Cr.)


  • Responsible for management and execution work of an elevated corridor of 2.10 Km having value of 230 Crore.
  • Improved project efficiency by streamlining processes and implementing innovative solutions.
  • Managed time, cost, quality and resource for construction of elevated corridor for decongestion of traffic for the running length of 3.5 Km.
  • Conducted progress review meetings with clients and outlined project progress review mechanism.
  • Coordinated with NHAI stakeholders for removal of hindrances, land acquisition work with respect to 3rd (B-H) section & pushed project progress as per scope of work finalized in contract .
  • Planning and managed resource for execution of casting of PSC girders, foundation and substructure works.
  • Reviewed drawings, BOQ & specifications for the elevated corridor with client and 3rd party design team.
  • Prepared construction methodology, baseline project schedule, WBS & resource requirements for submission and taken approval from client.
  • Management and coordination with vendors for fabrication work and development of casting yard with trolley system for precast prestressed I girders
  • Controlling cost by reconciliation and reducing wastage in issue of free materials to subcontractors
  • Prepared Quantity take off and verified billing works for Vendors and Sub Contractors
  • Negotiated contracts with vendors, securing favorable terms for the organization and improving overall project profitability.

Assistant Bridge Engineer

LEA Associate South Asia Pvt Ltd
2019.06 - 2021.09

Project: Additional Facilities for Lane 4 divide highway of NH-58 (Meerut- Muzaffarnagar Section) on EPC mode- (Project Cost- 210 Cr.)


  • Assisted in preparation of project budgets, maintain schedules and clubbing together as final documentation.
  • Oversaw proposal and bidding phases of construction.
  • Completed contract management work HAM, EPC and BOQ model
  • Evaluation of bids, process, type of contract and tender amount
  • Managed and supervised execution work for 3 numbers flyover, 5 Underpasses, 28 Culverts, 4 FOB, and 21 Km. drain works
  • Exposed to COD, price escalation/variation, Change of scope related to structures with reference to contract agreement (Schedule B)
  • Coordinating with HO design team for submission and approval of drawings, plan and profiles with respect to IRC, IS, MoRTH and other relevant codes for EPC project
  • Listed pending design approval, contract deliverable with Team Leader
  • Assisted SQS in preparation and calculation of EOT and Claims with formulas prescribed by NHAI
  • Reviewed quantity, claims, COS, Pre- COD and bill submitted by contractor
  • Responsible for testing of Bearings, RE wall panels and other components of flyover/bridge during construction
  • Carried out day to day supervision and inspection of ongoing construction activities as per specification and drawings
  • Provided all technical support required by site engineer, preparation of measurement sheet
  • Worked on PMS portal DATA LAKE for update of progress reports to client
  • Responsible for solving issues as per project standards and timeline

Project Lead- Transformation

OYO (Oravel Stays Private Limited)
2018.08 - 2019.05
  • Responsible for audit works and interior fit out work.
  • Discussing and Defining Scope of work with clients in close coordination with business development team.
  • Scheduling, assigning resource and estimation work for the given project.
  • Responsible for Planning of required resource, aligning vendor and managing them in terms of cost and timeline.
  • Execution work of interiors and modular furniture.
  • Weekly reported to Hub head about the progress and points of concern.
  • Managed change in scope, schedule and related cost to it.
  • Ensuring that OYO project scope work should be completed on given timeline.
  • Responsible for completion of organization scope of work in given timeline and making property live in terms of operations.

Post Graduate Trainee Engineer

ITD Cementation India Limited
2017.08 - 2018.08

Project: Construction of J5 oil berth at Jawahar Island at Mumbai Sea Port on EPC mode. (Project Cost- 320 Cr.)


  • Worked in planning and execution department for piling work in marine/offshore condition
  • Developed and manage project schedules, timelines, and milestones.
  • Created and update project plans, including resource allocation and progress tracking.
  • Conducting site visits to monitor progress and identify potential issues.
  • Coordinated with other departments (Store, precast and admin) for required resources and responsible for completion of work in given time cycle
  • Coordinated with clients for checking and verification works for RFI
  • Collection, analyze, and reporting project data, including progress, costs, and performance metrics.
  • Offshore erection of Piling gantry and launching girder for execution of piling and erection of precast works.
  • Hands on experience on piling rig equipment like RCD (MH Wirth), BG 28 (Bauer), Mait and Chisel-Bailer
  • Implemented Organization Integrated Management System for safety norms of labors, control and reporting system
  • Reduced cost for per bent pile works by controlling wastage of free issue materials and using scrap materials to sub-contractor.
  • Maintained bore log data and Estimated quantity of materials for ongoing construction activities

Assistant Engineer

Bihar Rajya Pul Nirman Nigam Ltd
2014.07 - 2015.07
  • Assisted in the development of technical specifications for engineering projects, ensuring accuracy and adherence to established guidelines.
  • Contributed to successful project completion by assisting with on-site inspections, testing, and quality control measures.
  • Determined budget, manpower, schedule and material needed to successfully execute projects.
  • Increased overall project safety by enforcing company policies and adhering to industry regulations.
  • Provided technical support during construction phases of a project including field supervision or inspection services.
  • Supervised work for precast post- tensioned segmental bridge (Double Cell)
  • Execution work for piling and precast department
  • Study of approved drawings, preparation of BBS and quantity estimation work related to site works
  • Coordinating with in house and client’s 3rd party for quality assurance
  • Maintained bore logs for piles, collected soil sample with documentation
  • Assisted team in drafting revised drawing, survey points checking with TBM and conveyed to senior staffs
  • Assisted Senior Engineer in fabrication and other work given by them

Education

MBA - Construction Project Management

RICS SBE, Amity University
Noida, UP
05.2017

B. Tech - Civil Engineering

NSIT, Magadh University
Patna, Bihar
06.2014

Skills

    Project Management

  • Project Planning
  • Cost Management
  • Contract Management (FIDIC & Non FIDIC types)
  • Stakeholder Management
  • Communication & Coordination
  • Risk Management
  • Market analysis and preparation of feasibility report
  • Documentation
  • Technical

  • Design and Drawing review
  • Quantity surveying and Billing
  • Precast and Prestress Engineering
  • Site Management and Supervision
  • Interior and Modular furniture Works
  • IT Skills

  • Microsoft Project
  • Primavera P6
  • Microsoft Office
  • Personal Traits

  • Adaptable
  • Problem Solving
  • Decision Making
  • Team Player
  • Interpersonal Skills

Timeline

Associate Manager - Project Management Office

Megha Engineering and Infrastructure Limited
2022.06 - Current

Deputy Project Manager

MRG Construction
2021.10 - 2022.04

Assistant Bridge Engineer

LEA Associate South Asia Pvt Ltd
2019.06 - 2021.09

Project Lead- Transformation

OYO (Oravel Stays Private Limited)
2018.08 - 2019.05

Post Graduate Trainee Engineer

ITD Cementation India Limited
2017.08 - 2018.08

Assistant Engineer

Bihar Rajya Pul Nirman Nigam Ltd
2014.07 - 2015.07

MBA - Construction Project Management

RICS SBE, Amity University

B. Tech - Civil Engineering

NSIT, Magadh University
Atul Raj