An adept professional with more than 15 years of cross-cultural experience across Site Execution/Supervision and Quantity Survey (BOQ/ COST Engagement, Rate Analysis) & Project Management in BUILDING Projects, METRO RAIL DEPOT Projects, HOSPITAL Project, WTP & STP Project.
Overview
16
16
years of professional experience
Work History
PROJECT ASSOCIATE & PROCUREMENT EXPERT
VOYANTS SOLUTIONS PVT LTD
02.2025 - Current
Assist client and Procurement/Contract Consultant (Arkitechno Consultants Pvt Ltd.) in preparing Tenders, Contracts and Other documents relate to Bidding for various projects of Transport Dept
Funded by World Bank
MANAGER PROJECTS-CIVIL
VEPL
12.2024 - 02.2025
Manage entire Site Jobs as per Planning and Projection including Documentations
SENIOR RESIDENT ENGINEER
VA TECH WABAG LTD (EPC)
01.2020 - 10.2024
Execute Civil Jobs of entire Project as per Approved Drawing with Daily & weekly well as Monthly Planning schedule to achieve Target as per Contractual Milestone
Finalize BOQ For entire Civil work
Check & Certify Sub Contractor Billing relate to Civil Jobs
Prepare entire documentations relate to Client Billing Milestone wise
PROJECT: 65 MLD STP PROJECT AT HOWRAH, WEST BENGAL
CLIENT: NMCG (National Mission for Clean Ganga) & KMDA (Kolkata Metropolitan Development Authority)
Consultant: Royal Haskoning DHV
The main purpose of this project is to collect waste water from entire Howrah via 03 nos Lifting stations and 01 nos pumping station and treating the same by ASP Method (Activated Sludge Process) and discharge The Treated water to River Ganga via Canal
STATUS: Commissioning is started from December 2023
Project Engineer-CIVIL
AECOM INDIA PVT LTD. (PMC)
01.2019 - 12.2019
Site Supervision & Certification of work as per Drawing & FQP Documentations of Site work
PROJECT: INDIA INTERNATIONAL CONVENTION & EXPO CENTRE
CLIENT: India International Convention & Exhibition Centre Limited (Department of Industrial Policy and Promotion Ministry of Commerce & Industry Government of India)
CONSTRUCTION ENGINEER-CIVIL
DEVELOPMENT CONSULTANTS PVT LTD. (PMC)
12.2014 - 12.2018
Site Supervision & Certification of work as per Drawing & FQP
Documentation of Site Work & Preparation of Daily/Weekly/Monthly Progress Report
PROJECT 3: 2 MTPA LEAD ZINC BENEFICIATION PLANT AT ZAWAR MINES, HZL, Client: VEDANTA (HINDUSTAN ZINC LIMITED)
PROJECT 1: SUPER-SPECIALTY HOSPITAL PROJECT, Kakdwip, West Bengal, Client: HRBC (Hooghly River Bridge Commissioners)
ENGINEER-CIVIL
ARABIAN CONSTRUCTION COMPANY INDIA PVT LTD.
06.2014 - 11.2014
Site work Execution as per Drawing & Planning, Quantity Survey & Sub Con Billing, Materials requisition & Reconciliation
PROJECT: THE 42 CHOWRINGHEE RESIDENTIAL HIGH RISE BUILDING PROJECT (G+62), CLIENT: MANI GROUP & ALCOVE
SITE ENGINEER L-3
CONSOLIDATED CONSTRUCTION CONSORTIUM LTD. (EPC)
06.2011 - 06.2014
Site Execution as per Drawing & Planning, Engineer IN Charge for Stabling Yard, Admin Building & Driver's Rest Building, Quantity Survey & BBS preparation
Subcontractor Billing, Materials Requisition & Reconciliation, Assisted for Client Billing Preparation & Certification of Site work Documents by Client & Consultant
PROJECT: CENTRAL PARK METRO RAIL DEPOT PROJECT, CLIENT: KOLKATA METRO RAILWAY CORPORATION LTD., CONSULTANT: MYCEL-GENERAL CONSULTANT
SITE ENGINEER (Execution, Quantity Survey, Client & Sub-Contractor Billing)
SMS ENTERPRISE
06.2009 - 06.2011
Site Execution as per Drawing & Contracts Agreement, Quantity Survey & BBS preparation