Client: HITES (HLL INFRATECH SERVICES LTD.)
- Customer: AIIMS
- Duration: February 2020 to June 2020
- Major item: Earth work, RCC, Brickwork, Finishing items etc.
Title: MBB Airport
- Client: Airports Authority of India
- Duration: December 2019 to February 2020
- Major item: Road Work, and finishing work Completed DLP with client satisfaction
Title: 2.3 kilometer length Flyover, Agartala
- Client: PWD Agartala
- Duration: October 2016 to December 2019
- Major item: Re-wall, Road work, Drain work
Title: Construction of100 MW gas based power plant at Monarchak.
- Client: Bharat Heavy Electrical Limited.
- Customer: NEEPCO.
- Duration: Since October, 2011–October 2016
- Major Item: GTG, STG and Pre-Treatment Plant, R.C.C. Works
Title: Construction of Academic Building ,in Techno University Agartala west Tripura
- Client: Techno University
- Duration: Since June 23 to March 25
- MajorItem: Earth work, RCC, Brickwork, Finishing items etc.
Title: Construction of D.M. Office, in Belonia South Tripura.
- Client: R.D. South Tripura
- Duration: Since April 25 to Till now
- MajorItem: Earth work, RCC, Brickwork, Finishing items etc.
Responsibilities Handled-
- Site Execution and Labor Management.
- Estimating the quantities.
- Preparing Bar Bending Schedule.
- Calculating the daily work done report.
- Dealing with Client and customer for various matters regarding Drawings and works
- Preparing PRW and Sub-Contractors bill.