Assistant Manager - HVAC ( MEP )

Godrej & Boyce mfg ltd
Vikhroli
06.2022 - Current
  • Accomplished multiple tasks within established timeframes.
  • Kept detailed records of daily progress to identify and correct areas needing improvement.
  • Evaluated suppliers to maintain cost controls and improve operations.
  • Maximized performance by monitoring daily activities and mentoring 10 team members.
  • Supervised labor costs and departmental expenses to remain in line with budget.
  • Handling over 200 manpower per day to improve site progress.
  • Planned and managed engineering projects and continuous improvement programs to reduce labor and costs.
  • Recommended process improvements to reduce unnecessary waste

Sr Engineer MEP

Listenlights pvt ltd
Mumbai
02.2022 - 06.2022
  • Defined engineering problems, collected data, established facts and drew conclusions to solve project issues.
  • Coordinated responses to RFIs issued by contractors for operations.
  • Supervised employees throughout design and execution of projects.
  • Completed projects consistently sticking to strict schedules and budgets from start to finish.
  • Handling Installation activity of HVAC system & Fire protection system.
  • Ensuring that all mechanical site activities are conducted under controlled conditions as per approved Shop Drawings, Method Statement, and Project Specification & Work Plan.
  • Monitoring installation of Chilled Water piping, Ducting, Insulation, AHU, and FCU, Air Terminals and all other Equipment and ancillary item as per drawings.
  • Ability & Strong technical expertise to perform independently, execution, testing of Sprinkler system, Hydrant system and drainage system.

Site Engineer - MEP

Voltas ltd ( teamlease pvt ltd )
Mumbai
09.2018 - 02.2022
  • Handling Installation activity of Water Cooled Central Air Conditioning system & Fire protection system.
  • Ensuring that all mechanical site activities are conducted under controlled conditions as per approved Shop Drawings, Method Statement, and Project Specification & Work Plan.
  • Monitoring installation of Chilled Water piping, Ducting, Insulation, AHU, and FCU, Air Terminals and all other Equipment and ancillary item as per drawings.
  • Ability & Strong technical expertise to perform independently, execution, testing of Sprinkler system, Hydrant system and drainage system.
  • Preparation of T&C reports and getting Inspection & Certification done from client]
  • Ensuring Proper coordination with Manufacturer and Supplier for site related issue
  • Site coordination with other service disciplines & proper reporting to Project Manager.
  • To coordinate with other MEP service engineering discipline.
  • Supervised and monitored daily task of 08 contractors.
  • Generation of De-snag as well HOTO documents & Project Handing Over documents & submission to client.
  • To ensure Safety Standards & Procedures are implemented & followed in accordance with contract requirements & Company guidelines.
  • Receive/action Request for Information (RFI) that apply to mechanical works
  • Carrying Work Inspection Request (WIR) & Material Inspection Request (MIR) With QA/QC Engineer.

Project Engineer

Blue star ltd ( Teamlease pvt ltd )
mumbai
07.2016 - 08.2018
  • Successfully installed 4 No’s of each 1,000 TR chiller & 4 No’s of each 1,200 TR Cooling tower.
  • AHU, CSU, FCU, TFA, HRW, PAC installation.
  • Installation of axial fan and Jet fan.
  • Reflex system (Chilled water makeup system) installation.
  • Transition activity (Snagging/De-snagging) for all technical equipment’s.
  • Preparing Daily DER Report, Daily HVAC activity Report, Monthly Management Report.
  • Performed all installation activities within timeline and increased knowledge as well.
  • Liaised with company executives and project managers to acquire resources to move projects forward
  • Communicated with industrial equipment installers to deliver technical support throughout project execution
  • Delivered concise instructions to technical team to maintain quality control
  • Identified technical risks within managed projects
  • Planned and managed engineering projects and continuous improvement programs to reduce labor and costs

Education

SSC - SSC

S.H.Jondhale Vidyamandir
Mumbai
06.2012 - 05.2013

Diploma in Mechanical Engineering - Mechanical Engineering

S.H.Jondhale Polytechnic
Mumbai
06.2013 - 05.2016

Skills

    HVAC installation and maintenance

undefined

Playing Cricket

3 Times Champion in VCC , 5 man of the match , 2 man of the series

Timeline

Assistant Manager - HVAC ( MEP )

Godrej & Boyce mfg ltd
06.2022 - Current

Sr Engineer MEP

Listenlights pvt ltd
02.2022 - 06.2022

Site Engineer - MEP

Voltas ltd ( teamlease pvt ltd )
09.2018 - 02.2022

Project Engineer

Blue star ltd ( Teamlease pvt ltd )
07.2016 - 08.2018

Diploma in Mechanical Engineering - Mechanical Engineering

S.H.Jondhale Polytechnic
06.2013 - 05.2016

SSC - SSC

S.H.Jondhale Vidyamandir
06.2012 - 05.2013
Hitesh PatilAssistant Manager HVAC - MEP Execution