Dedicated industry professional with history of meeting company goals utilizing consistent and organized practices with Aditya Birla Grasim and JK Papers Ltd. Skilled in working under pressure and adapting to new situations and challenges to best enhance the organizational brand.
Experienced in Pulp Mill Mechanical Maintenance (10 Years) & Projects (4 years) with over 14 years of experience in Pulp & Paper industry. Excellent reputation for resolving problems and improving customer satisfaction.
Reliable employee seeking Mechanical Sr. Manager position. Offering excellent communication and good judgment.
Hands on experience in maintenance and troubleshooting of Rotating Machines, static equipments, piping Networks etc. in either of the Pulp and Paper Machine area as well as Projects
Conversant with latest maintenance practices, lining up of maintenance contracts, spares procurement, budgeting etc. and be computer literate.
Specific experience in maintenance of Batch and Continuous Digester based Pulp Mill & 450 TPD Pulp Mill Erection and Commisioning.
• Worked on Pulp Expansion Project from 260 TPD to 360 TPD, contributing to significant capacity enhancement.
• Involved in Basic and Detailed Engineering, ensuring accurate planning and execution of project deliverables.
• Commissioned 2 Nos RO Plants in the ETP to address and mitigate water crisis challenges effectively.
• Developed strong relationships with stakeholders to facilitate smooth communication and ensure timely project completion.
Projects:-
For Vertical /Batch Digester pulp mill
Projects ETP:-
Erection and commissioning of
Projects Pulp Mill & Its Machine:-
Under RGP
Looking after following plant maintenance:-
New Projects:-
1. Successfully commissioned 450 TPD Pulp Mill at JK Paper Ltd.
2. Successfully erected and commissioned Decanter machines installation for dewatering secondary sludge,
3. Successfully erected and commissioned Screw press for primary sludge handling machine.
4. Successfully erected and commissioned UASB
5. Successfully erected and commissioned tertiary treatment plant.
Modifications old to new technology: -
1. Successfully erected and commissioned steam and condensate system in Sheeting machine supplied by Forbes Marshell.
2. Successfully erected and commissioned Drive of Brown stock washer from Journal to Bearing.
3. Successfully Modify 12 Pumps Gland Packing to Mechanical seal.
4. Successfully installed Softwater circuit for Mechanical seal cooling.
5. Successfully replaced one Digester 40 M3 during running of plant.
6. Successfully replaced Perforated Deck of Bleach washer 13.6 Mtr Long in house in 20 Hours.