NEOM Green Hydrogen Project, Kingdom of Saudi Arabia
Scope of Work: FCA, Fabrication Shop to installation on foundations of 22 units of H2 Storage Bullets & 32 units of PAR Modules and transport of several heavylift equipment for the project
Achievements:
- Coordinating, negotiating and finalising suitable BB MPP vessels for each shipment with assistance from the chartering team for the project and subcons for the pre-carriage and on-carriage scope for each shipment with assistance from the local deugro offices worldwide
- Manage complete operations for all HL/BB shipments for the NEOM GHE & HIDC project including but not limited to collection, pre-carriage to all major port in the world (trucking/barging), ocean freight to KSA ports, trucking and installation onto foundations at site
- Responsible for the complete project management of transport/shipping and installation of the SODC cargoes (H2 bullet tanks, & PAR modules)
- Coordinating, negotiating and finalising suitable deck carrier vessels for the SODC cargoes (H2 bullets & PAR modules) of the project with assistance from the chartering team
- Directly coordinating, negotiating and finalising subcons for the pre-carriage and on-carriage scope for the bullets and PAR modules
- Managing 3 deck carrier vessels up to capacities of 23,000 DWT in parallel over 12 voyages
- Coordinating between all stakeholders for the preparation of all technical documentation for the shipping aligning with fabrication and project schedules/requirements
- Managing and aligning 11 subcontractors operationally and technically to ensure smooth and flawless operations
- Managing the load out/in operations directly on ground, ensuring full QHSE compliance
GASCO LPG Expansion Project, Riyadh, Kingdom Of Saudi Arabia
Scope of Work: Transport and Installation of 9 unit of Bullets tanks (L63m*W9.5*H11.7m- 856 MT) from Vendor Facility to Project site around 490 kms
Achievements:
- Lead the FEED of the project along with the project owner, studied and ensured the transport was feasible with the dimensions of the bullets. Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 20 including engineers, operational staff and technicians
- Negotiated contracts with sub-contractors
- Successfully secured the phase 2 of the project during the execution of phase 1 of the project
VESTAS Dumah Al Jandal 400MW Windfarm Project, Kingdom of Saudi Arabia
Scope of Work: Transport of 20 sets of V150 WTG components from POD to the project site around 850kms
Achievements:
- Lead the 1st ever wind farm project in the kingdom
- Lead a project team of 37 including engineers, operational staff and technicians
- Completed the project successfully and with zero incidents
Petro Rabigh Turnaround 2020, Kingdom of Saudi Arabia
Scope of Work: Replacement of 10 units of condensers by elevated jacking and skidding during the turnaround and transport of all heavy lift equipment for the turnaround from laydown area to foundations
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 36 including engineers, operational staff and technicians during the outbreak of the COVID-19 and was able to complete the project safely and on schedule
Aluminum Bahrain Potline 6 Project, Kingdom of Bahrain
Scope of Work: Transport and Installation of Various Heavy Lift Equipment- Stack Sections, Panels Sections, Overhead Cranes, Filter Sections
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead the engineering team to design a bespoke solution for the transport of the panel sections to save time and cost for the client
- Setup the branch in the kingdom
- Oversee the financial and operational management of the branch during the project tenure
- Negotiated contracts with sub-contractors
- Lead a project team of 12 including engineers, operational staff and technicians
- Completed the project successfully and with zero incidents
- Successfully negotiated additional scope of work of USD 0.3 million
- Solved contractual disputes of USD 0.1 million
Saudi Aramco Ethane Deep Recovery Facility Project, Uthmaniyah Gas Plant, Kingdom of Saudi Arabia
Scope of Work: Transportation of 92 Heavy Lift equipment including the De-Methaniser Column (L76M*W8m*H9M-1156MT) from Various port and fabricators yard to the project site
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 24 including engineers, operational staff and technicians