Experienced QS with 6.5 Years of Experience in residential, commercial, and villa construction. Proven track record in cost control and Project scheduling, risk management.
Overview
7
7
years of professional experience
Work History
Sr Engineer QS & Planning
Greenmark Developers Pvt.LTD
12.2024 - Current
Controlled project costs by approving expenditures.
Determined equipment failure root cause and implemented solutions.
Enforced rules and regulations to keep working environment safe.
Monitored employee performance to keep projects on task.
Conducting the reviewed meetings with the head of the departments.
Contractor Finalization and Rate Negotiations.
Training Junior Engineers on industry-standard best practices.
Senior Engineer QS
L&W Building Solutions Private
08.2024 - 12.2024
Prepare payment certificate for subcontractors.
Preparing bill of Quantities and budget sheet.
Preparing variation order for subcontractors.
Preparing Client bill supporting Documents.
Material Reconciliation.
PO Bills checking with site Store material inward.
Preparation of full and final statement for Sub contractors.
Prepare payment certificate for suppliers.
Making Individual Workers data, preparing VRF and follow up to get Approval from MD Sir level in WEMS.
Preparation of cost report for Precast division.
Preparation of Profit & Loss report for Precast division.
Preparing rate for Precast element (Drain cover slab, Trench, Parapet wall, PT Slab etc..,).
Making of tracker for precast production report and dispatch report.
Preparing Quotes for Precast elements.
Preparing CS for safety material, consumables & Precast element.
Preparing PO for safety material, consumables & precast element.
Material follow up.
Engineer QS
Hallmark builders and developers
11.2019 - 08.2024
Prepare tender and contract documents, including bills of quantities.
Preparing of MIS and Monthly material reconciliations.
Undertake cost analysis for repair and maintenance project work.
Perform risk, value management, and cost control.
Advise on a procurement strategy.
Identify, analyze and develop responses to commercial risks.
Prepare and analyze costings for tenders.
Allocate work to subcontractors.
Provide advice on contractual claims.
Analyze outcomes and write detailed progress reports.
Value completed work and arrange payments.
Maintain awareness of the different building contracts in current use.
Assistant Engineer
MRKR Constructions
04.2019 - 09.2019
Supervision of the labour and machinery.
Preparing the DPR & DLR sheets.
Maintaining the work progress sheets.
Auto leveling and earth work quantity calculations.
Education
SSC -
A P Model School
Thamballapalle
01.2016
Diploma - civil Engineering
Govt Polytechnic College Nagari
Nagari
01.2019
Skills
MS Office
AutoCAD
Realx ERP
Quadra ERP
BIM
MSP
Performance evaluation
Project management
Accomplishments
Worked as Assistant engineer at HNSS Canal Project near Madanapalle.
Completed Hallmark vicinia site (2B+G+12F) as Trainee Engineer (2019-2022).
Completed Hallmark vest (B+G+5F) and 5A villa projects as Engineer QS.
Working as Senior Engineer QS at RMZ necxity and Spire Projects (5B+G+21F and four Towers) under L&W constructions Pvt.Ltd.
Handling of Gateway & Majesty which is containing of (6B+G+47F) & 410 Villas.