Seeking a challenging position in an esteemed organization to perform my skills and abilities that ultimately participate in the growth of the company. Always willing to learn new things through experience.
Overview
18
18
years of professional experience
Work History
Sr. Executive
Reliance Jio Infocomm Ltd
05.2017 - Current
Total Execution Done Mumbai Area
Approx. 350 Km ROW applied in Mumbai/Navi Mumbai/Thane/Bhiwandi Area.
Approx. 350 Km T&D work done in Mumbai/Navi Mumbai/Thane/Bhiwandi Area.
Managed Local issue, Political issue at site during execution
End to End Project execution which consist activities such as Field Survey, BOQ planning, Budget approval, rollout and Handover to Planning with handling Team responsible for execution.
OFC Rollout through various methods such as HDD, Open Trenching, Micro Trenching & Aerial Cabling.
Responsible for managing Technical glitches in projects successfully.
Handling Underground Utility Survey Engineering Team.
Coordination with Authorities for ROW, Vendors, Engineers for daily activities.
Liasioning with Local Public for smooth execution of Project.
FTTH work like IBD work, cable pulling, Splicing & end to end connectivity of OLT/FSA/DSA.
IBD work for last mile of site connectivity and Enterprises customer.
Material management techniques and procedures.
Fiber cable pulling/Blowing Splicing, Termination for EnodeB and ILA site Integration.
Ensuring Quality, Audit, Health and Safety measures on site during project deployment.
Material Coordination & Billing certification.
HOTO to Operation & Maintenance Team.
Parent-RIL
OFC Engineer
M/s. Larson & Turbo Pvt Ltd
01.2017 - 05.2017
Planning for Root survey
Make SLD (Single Line Diagram)
Make application for individual Work authority
Arrange req. material like HDPE pipe, Fiber cable etc.
Start work ( Make Day wise Site Measurement sheet with BSNL Engineer)
While Doing Open Trench, HDD, work Maintain proper SAFTY norms.
Cover all OT work MH pit work HDD work with proper barricades also maintain Labor safety.
In QUALITY work while doing Open Trench we have to maintain proper Depth or if any Deviation’s in depth we have to protect our HDPE duct with DWC pipe or GI pipe Specifications And covering with PCC material.
While doing HDD or MT work we have to maintain proper depth. for hdd work (above 2.5 mtr ) Define on our company requirement
Engineer
Reliance Jio Infocomm Ltd
12.2011 - 12.2016
Planning of OSP making & maintenance
Implementation of OSP work
Responsible for drafting plans, Often when working with municipalities Trenching or HDD permits by submitting drawings
Producing estimate (capex) of material & services required, taking of bills & data maintenance
Planning and implementation of termination and splicing of OFC to interconnect the network element in ring.
Planning of OFC Network (feeder) to connect various network elements in ring in order to have path diversity to avoid outage and carrying out its implementation.
Carrying out field Surveys, planning and execution of fiber Network & carrying out acceptance test on the same.
Field Engineer
TATA TELESERVICE MAHARASHTRA LTD.
08.2008 - 12.2011
Surveying for Planning and Designing of OSP.
Coordination with ROW team for the Permission from ROW Authorities like Mu Municipal Corporation, State Government, MIDC, NMMC, KDMC, TMC, PWD.
Preparation of Indent for Material.
Planning and execution of work.
To coordinate between different contractors and agencies to maintain the project speed at the site.