Electrical Project Manager with 10 years of experience in Electrical Project Design, Tendering, Planning, Purchase in Automobile Industry plant setup projects. Seeking challenging assignments in Site and Project Management with a growing industry. Willing to work as a key player in a challenging and a creative environment.

Work History

Electrical Project Manager

G-Corp Power Pvt Ltd
Bangalore, Karnataka
2016 - Current

Responsibilities:

§ Preparation of Electrical Project proposal documents and techno-commercial offers for modification & new projects.

§ Preparation of project execution schedule to achieve in time installation and commissioning.

§ Preparation of Project budget sheet, Sales & Purchase ledger and Project cost sheet.

§ Providing project scope to selected vendors and obtaining costing.

§ Selection of suitable vendors for execution of project.

§ Administering contractors scope in Design, Fabrication, Installation and Commissioning Project.

· Attending daily morning meetings with customer/sub-contractors progress meeting and closing meeting.

Achievements:

· Suzuki Motor Gujrat(July 2016 to May 2018): Led a team of approximately 100 contractor members for Electrical Project Implementation with suitable material handling, equipment handling and RA-Bill preparation for installation & commissioning of HT & LT electrical equipment etc at New Plant Setup for Suzuki Motor Gujarat.

· TKAP934K Project(June 2020 to April 2021): Developing complete plant detailed Electrical load design, shop drawings including BBT layout, cable tray layout, PDP layout, Preparation of cable schedule, PDP schedule, Preparation of BOM/BOQ, Power socket layout etc for TOYOTA 4th generation vehicle Engine spare parts manufacturing plant located at Bidadi, Bangalore.

A. G-CORP POWER PVT LTD, Bangalore: (July’2016 ~ Present)

G-Corp Power Pvt Ltd is an ISO 9001 -2008 certified company providing Electrical Services across the India. G-CORP started with the intention to provide 360 degree solutions to G-CORP ESTATES, as a subsidiary established in 2014, G-Corp Power Pvt Ltd has made long strides in the electrical turnkey industry. Currently G-CORP exhibiting turnkey services in the states of Karnataka, Haryana, Gujarat & Tamilnadu and its head office in Bangalore, Karnataka, india.

Designation: Manager - Projects

Duration: July 2016 to Present

KEY DELIVERABLES

Ø Responsible for planning and scheduling for completing the project before due date, manpower planning, and certification of the project completion.

Ø Accountable for site evaluation for modification or new projects & preparation of BOQ/BOM.

Ø Actively interacting with department like projects, sales, account and design team during or after the installation.

Ø Preparing project reports to update senior management on the project progress and showcase the project value.

Ø Looking for ways to increase the project profitability and reduce expense where possible.

Ø Managing project deliverables in line with project plan and ensure deadlines are met.

Projects Handled:

Ø Toyota Industries Engine India Private Limited(TNGA) New Engine Plant Setup Project at Jigani, Bangalore

Ø Toyota Kirloskar Auto Parts(TKAP934K) New Plant Stup Project at Bidadi, Bangalore

Ø Wistron Manufacturing India Plant at Yashwantpur, Bangalore

Ø Tokai Rubber Auto Parts India Pvt Ltd Plant Expansion Project at Harohalli, Bangalore

Ø Yanmar Engine Manufacturing India Pvt Ltd at Chennai

Ø Toyota Kirloskar Motor Plant Expansion Project at Bidadi, Bangalore

Ø SUZUKI MOTORS GUJARAT New Plant Setup at Hansalapur, Ahmedabad, Gujarat

B. Southern Electric Company, Bangalore: (Jan’2012 ~ June’2016)

Southern Electric Company is one of the leading Class 1 Electrical Contractors established in the year 2005 and carrying out projects on Turnkey Electrification of all type of industries and power plants in the state of India.

Designation: Project Engineer

Duration: Jan 2011 to June 2016

KEY DELIVERABLES

Ø Accountable for electrical project implementation as a Project In-Charge.

Ø Accountable for morning tool box meeting, instruction to team members on daily activity schedule, safety training.

Ø Preparation of DPR, weekly schedule, monthly schedule.

Ø Responsible for daily, weekly, monthly schedule review meeting with client.

Ø Responsible for preparation of documentation like material inward, work progress monitoring, preparation of joint measurement report and interaction with financial team to prepare monthly invoice etc.

Ø Providing inputs to prepare as-built drawing and final handing over.

Projects handled:

Ø Toyota Kirloskar Auto Parts Pvt Ltd.(New Engine Line),Bidadi Industrial Area, Bangalore

Ø BANDO India Private Limited, Narasapura Industrial Area, Kolar.

Ø EXEDY Clutch India Private Limited, Narasapura Industrial Area, Kolar.

Ø Kirloskar Toyota Textile Machinery Ltd, Jigani Industrial Area, Bangalore.

Ø Toyota Kirloskar Auto Parts Pvt Ltd.(Transmission Line-EC 50 Project),Bidadi Industrial Area,Bangalore

Ø Britannia Industries Ltd(R&D),Bidadi Industrial Area,Bangalore

Education

BE EEE - Electrical & Electronics Engineering

Siddaganga Institute of Technology
Tumkur
05.2008 - 06.2011

Diploma - Electrical, Electronics Engineering Technologies

K.L.E’s Polytechnic
Hubli
06.2005 - 05.2008

PUC - Science Education

Dr. A V Baliga College
Kumta
06.2003 - 05.2005

10th - undefined

Bhadrakali high school, Gokarna

Skills

    Project Management, Strong decision maker,Team Work, Service Focused

undefined

Timeline

Electrical Project Manager

G-Corp Power Pvt Ltd
2016 - Current

BE EEE - Electrical & Electronics Engineering

Siddaganga Institute of Technology
05.2008 - 06.2011

Diploma - Electrical, Electronics Engineering Technologies

K.L.E’s Polytechnic
06.2005 - 05.2008

PUC - Science Education

Dr. A V Baliga College
06.2003 - 05.2005

10th - undefined

Bhadrakali high school, Gokarna
Naveen NaikProject Manager_Electrical