In quest of challenging assignments in Project Site co-ordination /QS Contract Management & Planning in the domains of Infrastructure/Pilling, Tunneling /Renewable Energy with an organization of high repute.
Location Preference: Pan World
A budding professional with more than 10 Yrs. of experience in site co-ordination, billing (Q S) & Planning and Contract Management.
Project Management, Earned Value Management, Schedule Management, Value Engineering.
Forensic delay analysis and EOT Claim as per guideline of Society of Construction Law and AACE.
Prolongation claim, variation order, timely notification of claim and response.
Focus on value, coordination with site team.
Effectively engage with stakeholder, experience in Primavera P6 and Microsoft Project, Dashboard.
Cost control, Material reconciliation, Rate analysis, budgeting, cashflow etc.
Results-driven Construction Project Control Manager with extensive experience in planning, implementing, and completing diverse construction projects. Proven track record of preparing accurate construction documents, estimating costs, and managing budgets to ensure timely project delivery. Recognized for executing strategic business initiatives that enhance profitability and improve operational efficiency. Committed to driving continuous improvement and fostering collaborative team environments.
Overview
10
10
years of professional experience
2
2
Certification
Work History
Project Control Manager
Statkraft India Pvt Ltd
Guptkashi
05.2024 - Current
Project: Mandakini Jal Urja 76 MW HP
Project Value: 750 INR Cr
Accountabilities:
Prepared Detail work Programme Schedule (Baseline Schedule) in Primavera P6 to complied by DCMA, project Controlling and Monitoring with the help of EVM
Drafting, reviewing, and monitoring contracts across various types and scales
Initial Budget preparation for Project and finding risk appetite at P50 and P70 for contingency fund.
Quantitative Risk Assessment with the help of Primavera Risk Assessment (PRA)
PO and Work order preparation, Contract formation FIDIC Red Book
PRW rate analysis, Variation Order claim and other Claims
Preparation of Planned vs Achieved (Financial and physical)
S-Curve Preparation, value engineering, Budgeting, cashflow preparation, cost control
Micro planning, pre identification of risk, monitoring, mitigation work
Progress tracking and monitoring with the help of Earned value management.
Rishikesh to Karan Prayag Rail Line Project (26 Km Tunnel) NATM with 4 Major railways bridges (Pkg-03)
Project Value: 2076 Cr
Accountabilities:
Prepared Detail work Programme Schedule (Baseline Schedule) in MS Project to complied by DCMA
Co-ordinates with site team to get the row data and prepare report and dashboard
Tracking and monitoring Schedule as per actual, fastraking, crashing Schedule if necessary
Preparation of Planned vs impacted Schedule
Rate Analysis for Additional Item /Non Schedule item as per IRSSOR, CPWD, Mort&H, CWC guideline and Indian standard
PRW rate analysis, Variation Order claim
Preparation of Planned vs Achieved (Financial and physical)
S-Curve Preparation, value engineering, Budgeting, cashflow preparation, cost control
Coordinate with contract team for EOT Claim and Idle Claim with substantial document
Contractual Correspondence/Notice of claim with client and PMC through PIMS(Siso)
Coordinate with site team and Preparation of Material indent month wise and quarterly wise
Review DPR and MPR for final submission to client
Micro planning, pre identification of risk, monitoring, mitigation work.
Assistant Manager
Larsen & Toubro Ltd, Chenab Valley Power Project Pvt Ltd
09.2020 - 08.2021
L&T Construction (Heavy Civil Infra-IC)
Project: EPC of Two circular shaped Head Race Tunnel –Twin of Length 7.35Km each to be excavated by Two New TBMs and associated works for Pakal Dul HEP J&K
Project Value: 2576 Cr
Accountabilities:
Prepared Detail work Programme Schedule in Primavera P6 and accountable for DCMA 14-point assessment compliance
Tracking and monitoring Schedule as per actual with risk management
Preparation of Impacted Schedule
Contractual Correspondence and timely notification
Client Running Account Billing, Variation order preparation, Rate analysis
Price Variation Bill on monthly Basis and preparation of Variation order
Delay Analysis by As Planned VS as Built Method and Impacted as planned method
Micro level planning and data analysis to forecast the work schedule and financial schedule.
Project Engineer
Patel Engineering Ltd, Ircon International Ltd
02.2019 - 07.2019
Project: Udhampur-Srinagar Broad Rail Line (USBRL), Railway Tunnel (NATM) Package-T15, T14 including Bridge No-64
Project Value: 1740 INRCr
Accountabilities:
Client Running Account Billing
Price Variation Bill on Quarterly Basis
Rate Analysis for Underground Additional Item as per CWC Guideline
Preparing the Billing Document (ATSS, Section for Excavation, Shotcrete etc.)
Co-ordinate with site team regarding supporting documents.
Sr. QS and Planning Engineer
Vertex International, Angelique International Ltd, Vertex International Pvt Ltd
To make a Construction Schedule in MS Project, find Slack time & Critical Path So that no Delay Occur
To make Construction Methodology and submitted to Client for approval
Rate Analysis for Underground work (Excavation, Supports such as Rib Erection, wire mesh, SFRS, fore polling, open work (RCC Structures), idle claims for manpower and machineries
To maintain & make all kind of execution drawing, DPR and site material reconciliation
Preparing the Execution Plan for different construction activities & selecting the appropriate techniques and sequence of events for the particular project
To Claim a bill on Running Account and monthly basis PRW Payment
Make MPR, QPR and Review Sheet and conduct meeting to monitor the process
Drawings study and preparation of material requirement for Execution work
To maintain and manage the manpower & material at site so that work couldn’t be hampered.
Engineer
LANCO Infratech Ltd
12.2015 - 11.2017
Project: 38x2 MW LANCO Mandakini Hydro Electric Power Project (Phata, Uttarakhand) Billing & Planning.
Worked in a Dam Site as a trainee Site Engineer under L&T Construction.
Trainee Engineer
Tehri Hydro Development Corporation Ltd
07.2011 - 07.2011
Education
PGP - Quantity Surveying And Contract Management
National Institute of Construction Management & Research
01.2020
B.Tech - Civil
Lovely Professional University
Lovely Institute of Technology & Science
01.2013
12th class -
State Govt
G.I.C Kirtinagar
01.2008
10th class -
State Govt
G.I C Pipali
01.2006
Skills
SOFTWARE SKILL SET
Designing and analysis tools like Auto CAD (2013, 2016), Auto Desktop-2014, MS Project-2013, 2019, Primavera P6 (V194)
Utilities: MS Office 2003 and 2007 (Word, Excel and PowerPoint), Window 7 & 8, XP, SAP MM Module Internet ability
LANGUAGES KNOWN
Hindi, English, Punjabi, Garhwali
Certification
PMI-Membership PMI ID: 8186961, PMP Certified Professional
Certified Quantitative Risk Manager.
Additional Information
PERSONAL DOSSIER
, Date of, -1989
Sex - Male
Marital Status -, Passport No - M8729080
Current CTC - 22.22 LPA + Perks
Notice Period - 2.0 months
Permanent Address - Dehradun Uttarakhand
Present Address - Phata byung HEP Uttarakhand
Driving License - LMV- Available