

Detail-oriented, organized, and meticulous employee. Works at fast pace to meet tight deadlines. Enthusiastic team player ready to contribute to company success.
Knowledgeable [Desired Position]. Successfully led cross-functional teams to complete complex engineering projects on time and within budget. Demonstrated proficiency in project management and problem-solving, contributing to continuous process improvements.
MAINTENANCE WORK
200KVA to 50MVA Transformer Testing & Charging, Distribution Transformer & Power Transformer Commissioning & Maintenance, OLTC Panel, RTCC Panel, Marshalling Box(Alarm Systems), Annunciators, Oil Leakages All type of Transformer Work, Bus duct, Earthlings Systems, Power monitoring & Control Systems, ACB, VCB, SF6 Breakers Servicing, 1 HP to 750 HP HT-LT Motors & HT-LT Panels, 33 KV Substation, Sump Pumps & Panels, Panel Board (DP),Etc All Equipment are handled Schedule SOP & PPM (Weekly, Monthly, Quarterly, Yearly) Spare management, Time management, and crises management
Looking into the installation of utility such as ACDB, AC, DG, SMPS, commissioning of AC & DG, SMPS Maintain Shift Activities Looking into the maintenance & breakdown of utility such as 180 KVA DG SET, SMPS, SUBMERSIABLE PUMPS, RO water pumps, scrubber pump, MOTORS FROM 1 HP TO 60 HP, 90HP, 120HP, VFDS (ABB,Schnider MAKE) ETC
PROJECTS WORK
Sensors Installation Motors,Pumps,Submersible Pump &, Dry Pit Submersible pumps All Types of Pumping Stations
Supported Equipment’s installation & Commissioning(UPS,Network Rack,Cabinet,Junction Box,Earthings) Up to 300mm Cable Tray and Cable Laying Installation work
Communication with client and smoothly run projects
Planning & management of distribution lines and substation works
Planning of strategies of Erection, Commissioning & Testing of substation & allied distribution work
Execution of 33 KV Lines, 11 KV Lines, LT Lines & Distribution transformer centers Execution of 33/11 KV substations, 33 KV Bays & 11 KV Bays
Execution of all the O/H as well U/G cable works of 33 KV, 11 KV & LT line
Execution of all the distribution network activities with solution of all the row problems Subcontractor handling with all the technical support with project specifications
Control cabling & termination works
Inspection of Electrical materials, Drawing approval & Material Management
Electrical maintenanceTechnical Support
To maintained the plant by assessing its performance and estimate cost of replacement of plant member (pipeline, valves, pressure gauge, air and water filter) Planning & management of distribution lines and substation works Planning of strategies of Erection, Commissioning & Testing of substation & allied Distribution works Material reconciliation & billing of all sub-contractors To trouble shoot the electrical & Instrumentation problems during commission phase To perform the testing of MCC Breakers along with vendor using Kit CP-100 (Single Phase)
To maintain 480 kw HT Motors, HT-LT Panels, 33kv Substation For Pumping stations, Swara get reatment Plant & Water Treatment Plant Execution of Corrective & preventive Maintenance activities for Shutdown Activities as per planning schedule To supervise the Installation & Commission of Electrical Distribution boards, VFD Panels, To supervise the Installation & Commission of Electrical Distribution boards, VFD Panels, Dimmer Panels, Lighting DBS as per the drawings & Equipment layout
Project management
Analytical thinking
Schedule management