Project : Mahua (DDR team)
Client : Qualcomm
HM’s : HSC_NOC_MSOUTH_LEFT
Inst Count : 4.6 Million with 4 macros
Layers : 15
Technology : TSMC 3nm technology
Ports : 54k
Frequency : 1.24ghz
Role : PnR.
Tools : Innovus
Duration : 2024 SEP to 2025 APR
Challenges :
1.Involved in multiple floorplan experiments to converge place congestion and timing.
2. Here I have FT ( 15K feed through ) ports because of ft’s buffering I saw huge congestion and tried multiple experiments to reduce the hotspots in sequential manner.
3.Timing was bad for few paths applied weightage effort high and created path groups so that I got better improvement.
4.Since there is huge inst count and hotspots facing so many shorts and DRC's where we have tried many experiments to get it reduced.
5.In ECO phase due to less space availabilty as utilization reached more than 60% after route stage faced a lot of issue in adding new cells for timing convergence, signoff activities and reducing crosstalk, noise , maxcap, maxtran.
6. Manually routed lot of nets in higher layers due to high crosstalk, noise and bad nets where routed in lower layers
7. Involved in closing all the signoff checks like PV, PDN, FV and CLP.
Project : Mahua (DDR team completely worked on FLOORPLAN ACTIVITY )
Client : Qualcomm
HM’s : HSC_NOC_MSOUTH_LEFT, HSCNOC_MSLICEHM0
Inst Count : 2.8 Million with 45 macros
Layers : 15
Technology : TSMC 3nm technology
Ports : 30K
Role : FLOORPLAN
Tools : Innovus .
Duration : sep 2024 to nov 2024
Challenges :
1.Involved in multiple floorplan experiments to converge place congestion and timing.
2.Because of macro count seeing high congestion in between macros channels.
3.Cleaning CI checker (TCIC checks) is very critical for this hm where lot of rules to be followed in order to get clean floorplan.
4.Most of the memories were abutted because of abutment seeing high net lengths so that timing is going bad.
5.Involved in signoff activities like PDN, CLP, FV and PV for floorplan closure.
Project : Bonito (DDR team)
Client : Qualcomm
HM’s : hm_monaq_channel_tile
Inst Count : 500k
Layers : 12
Technology : TSMC 4nm
Ports : 8k
Role : Floorplan & PnR
Tools : Innovus
Duration : Jan 2024 to sep 2024
Challenges :
1.Handled one channel tile with no macros and huge FT dominated block with 8K where Congestion , crosstalk , noise and all DRV, DRC issues are difficult to close them.
2.As there are more FT's lot of customized FT buffering done horizontally where we have faced unavailability of horizontal resources and found lot of cross talk and noise due to parallel running of the nets in same layers.
3. Tried resolving them using higher layers and higher drive strength cells to overcome them.
4. There are lot of timing failures of these FT paths due to strict budget issues given.
5. Involved in closure of all signoff activities and in BTO struggled in closure of DRV's.
6. Also in parallel worked on other Hm's on signoff closures and in absence of other Hm owners