Experienced Site Civil Execution Engineer with over 11 years in metro projects. Specialises in project management and site engineering for major metro structures, including underground stations, tunnel work, and elevated station finishes.
Overview
1
1
Language
11
11
years of professional experience
Work History
Site Engineer
DB Engineering & Consultants with MPMRCL
Indore
2022.03 - Current
Company Overview: Working on the MPMRCL Indore Metro Project.
Coordinated with MPMRCL to implement Quality Management System, ensuring compliance with project standards.
Executed project activities, contributing to successful completion of metro depot construction.
Oversaw structural works for depot buildings, ensuring adherence to design specifications across various building types.
Working as a Depot Quality Engineer and working on different activities.
Creating development plans and project documentation related to all Depot works.
Interacting with the client and understanding requirements.
Coordinate with team members in developing structure quality and project requirements.
Completed earthworks in designated areas in depot areas.
End-bearing pile works.
Project: -Construction of Rolling stock and workshop Gandhinagar metro depots.
Client: -Indore Metro Rail Corporation -MPMRCL.
Site supervision Engineer
TYPsA Group
Kanpur
2020.09 - 2022.02
Working as a Supervising site Engineer in the Underground segment casting yard and working on different projects.
Executed project activities to facilitate construction progress and ensure alignment with project timelines.
Establishment and Maintenance of Quality System and Monitoring Site Activities to ensure Quality.
Supervise Segment ring casting, Pre-cast and Concrete Mix Design (M-40, M-50, M-55, M60).
Ring Casting Checking for Tunnel, Station, and Finishing Work.
Sampling and Testing of Construction Materials, Calibration of Lab Equipment, Mix Design of Normal, Heavy and Special
Conducted thorough testing of project deliverables to ensure adherence to quality standards and specifications.
Conducted daily inspections of lab test results to ensure accuracy.
Project: Design and construction of a tunnel from the start of the elevated ramp (after Motijheel Metro Station) to the end of Nayaganj Station, including four underground metro stations (viz.) Chunniganj, Naveen Market, Bada Chauraha, and Nayaganj) and ramp including Architectural finishes, E&M, TVS, ECS, etc. on Corridor 1 of the Kanpur MRTS Project in Kanpur, Uttar Pradesh, India.
Client: Kanpur Metro Rail Corporation - UPMRC.
Developed project documentation and collaborated with client to clarify requirements and expectations.
Coordinated with team members in developing structure and project requirements. Surveyed and handover of the project land, and associated site clearances.
Developed casting yard for segment casting, Korea mould for casting tunnel segment, and Korea mould preparation, dimension checking, and cleaning of mould.
Steel cage preparation and making a cage for segment casting.
Steam curing of segment, after curing completion, de-mould and lift the segment.
Tilted the segment and finish the surface before applying the curing compound.
Segments stacked as per approved method statement.
Review ITP, QAP, PQP, method statement, and mix design.
Heavy Concrete and finishing work.
Site Engineer
Ayesa India Pvt.Ltd
Kanpur
2020.02 - 2020.08
Company Overview: Working on the construction of an elevated viaduct and stations for Kanpur Metro.
Project: Construction of elevated viaduct and 9 nos. Elevated station (viz. IIT Kanpur Station, Kalyanpur Railway Station, SPM Hospital Station, Kanpur University Station, Gurudeva Chauraha Station, Geeta Nagar Station, and Rawatpur Railway Station. Lala Jaipat Rai Hospital Station and Motijheel Station, including a special span on the Priority Section of Corridor 1, Phase 1 of Kanpur Metro at Kanpur, Uttar Pradesh, India.
Client: Kanpur Metro Rail Corporation - UPMRC.
Worked on the construction of an elevated viaduct, and stations for Kanpur Metro.
Supervised site activities, directing labour and resources to meet project milestones.
Executed project activities focused on planning and documentation to support successful project delivery.
Developed comprehensive project plans and documentation while engaging with clients to clarify requirements.
Interacting with the client and understanding requirements.
Working as a Quality Engineer and engaged in various activities. Creating development plans and project documentation.
Establishment and Maintenance of Quality System and Monitoring Site Activities to ensure Quality.
Coordinating with team members in developing structure and project requirements. Survey and handover of the project land, and associated site clearances.
Heavy Concrete and finishing work.
Conducted thorough testing of project outputs to ensure quality standards.
Coordinating with team members in developing structure and project requirements. Survey and handover of the project land, and associated site clearances.
Create development plans and project documentation.
Coordinating with team members in developing structure and project requirements.
Construction of pile, pile caps, pier, pier caps, U-girder, and T-girder.
Adapted work schedules to align with changing site conditions.
Monitored concrete batching and placement processes, ensuring adherence to safety and quality standards.
Monitored concrete batching and placement processes, ensuring adherence to safety and quality standards.
Working as a Supervising Quality Engineer in the Underground segment casting yard and working on different projects.
Executed project activities to ensure alignment with project goals and client specifications.
Maintained quality system, monitoring effectiveness through regular audits and surveillance to uphold project compliance.
Supervised segment ring casting and concrete mix design (M-40, M-50, M-55, M60) to maintain quality standards throughout production.
Conducted comprehensive testing of project works of the project.
Ensuring in process Inspection during Pre-pour Inspection, Concrete Production, Concrete Placement, Drawing and Work Procedures.
Project: Design and construction of the tunnel from the start of the underground ramp (near Charbagh Metro station) to the end of the underground ramp (near K.D.). Singh Babu Stadium Metro Station, including three underground metro stations (Hussainganj, Sachivalaya, and Hazratganj), including architectural finishes, E&M, TVS, ECS, etc. on the North-South Corridor of the Lucknow MRTS, Phase 1A Project, at Lucknow, Uttar Pradesh, India.
Client: Lucknow Metro Rail Corporation (LMRC).
Created development plans and project documentation. Interacting with the client and understanding requirements.
Coordinate with team members in developing structure and project requirements. Survey and handover of the project land, and associated site clearances.
Developed casting yard for segment casting, Korea mould for casting tunnel segment, and Korea mould preparation, dimension checking, and cleaning of mould.
Steel cage preparation and making a cage for segment casting. Steam curing of segment, after curing completion, de-mould and lift the segment.
Tilt the segment and finish the surface before applying the curing compound. Segment stack as per approved method statement.
Checking lab test inspection every day.
Oversaw the checking of ring casting processes for Tunnel work.
Review ITP, QAP, PQP, method statement, and mix design.
Site Engineer
Canon Fasteners
Lucknow
2015.08 - 2017.05
Client: - Lucknow Metro Rail Corporation (LMRC).
Executed project activities to ensure alignment with client specifications and quality standards.
Acted as a Quality Engineer and oversaw various projects.
Ensuring in process Inspection during Pre-pour Inspection, Concrete Production, Concrete Placement, Drawing and Work Procedures.
Maintained Quality System, conducting audits and surveillance to monitor and enhance compliance and effectiveness.
Creating development plans & project documentation.
Interacting with the client & understanding requirements.
Creating development plans and project documentation. Interacting with the client and understanding requirements.
Testing the works of the project.
Coordinate with team members in developing structure and project requirements. Survey and handover of the project land, and associated site clearances.
Project: - Lucknow metro rail corporation LKCC-04 Civil, Architectural Finishes, water supply, sanitary Installation, drainage, external Development, firefighting, fire Detection and Elevated stations from Transport Nagar to Charbagh on priority section on North-South Corridor of Lucknow MRTS Phase 1A.
Performed masonry work using fly ash blocks for wall construction.
Completed plastering on roofs and walls, both interior and exterior.
Finalised all ceiling works, including false and metal ceiling installation, along with wall and floor finishes. We completed the other carpentry work such as finishes around interior doors, handrails, frames, and trim.
Education
B. tech - Civil
Amity University
Uttar Pradesh
2015-01
Intermediate - Mathematics
U.P. Board
Gonda, UP
2009-01
High School - Science
U.P. Board
Gonda, UP
2007-01
Skills
Project Management
Subcontractor performance monitoring
Site office management
Professional Goals
Career development
Software Proficiency
C/C programming
Concrete mix design
Site inspections
Quality assurance
Site supervision
Tunnel segment casting
Client coordination
Quality control assessment
Personal Details
Language known : English, Hindi and German (basics)
Personal Skill/Attributes/ Interests /Hobbies
Good Presence of Mind., Active, Analytical Approach and Reasoning Ability, Quick Lerner, Dedicated., Readings book of science of fiction, Football, Cricket., Listening Songs.
Disclaimer
Prashant Dubey Digitally signed by Prashant Dubey Date: 2025.04.02 10:06:08 +05'30'
Site Engineer at INTERGRITY ENTERPRISE LTD (UNICEF) CONSTRUCTION OF SANITATION FACILITIES IN SCHOOLS & HEALTH CENTERSite Engineer at INTERGRITY ENTERPRISE LTD (UNICEF) CONSTRUCTION OF SANITATION FACILITIES IN SCHOOLS & HEALTH CENTER