(Electrical & Automation Engineer with 14 years of experience) in projects, maintenance and business development and analytical problem-solver with talents for team building, leading and motivating, as well as excellent customer relations aptitude and relationship-building skills. Proficient in using independent decision-making skills and sound judgment to positively impact company success. Dedicated to applying training, monitoring and morale-building abilities to enhance employee engagement and boost performance.
Actively participated during commissioned 1.4 MTPA Bar Mill (Danieli)
1.Indenting the material, getting the quotations from the vendors. 2.
2.Technical evaluation and Rating of the various vendors and follow up
for procurement.
3. Erection and charging of 33kV,6.6kV switchgear, transformers, MCC
Instruments fixing, wiring and IO checking from PLC in the Mill area.
4. Profibus and OFC networking for RIO’s, drives and instruments
5. Communication setup with drives and MCC’s from Siemens S7-400
6. Programming with S7-400 for mill stands operations and rolling
7. Siemens G120, S120 and ABB ACS800 multi drives commissioning.
8.Support for development of SCADA pages for Mill using WinCC and
also modification of program for stabilisation of processes and to
avoid delays of production.
9. Erection and commissioning of the WATER TREATMENT PLANT
supplied by Sideraulic, Italy for BAR mill. Activities included
commissioning of 6.6Kv switchgears, HT motors, LT switchgears &
motors and all associated instrumentation's.
Contract Management
undefinedPMP - Project Management Professional
Execution Projects as PM:
Project #1: Erection and Commissioning of Billet Weighing System at Bar Mill. (Mar 2016- Jan 2017)
This project was about installation of billet weighing system to calculate real billets weight, the actual yield and the wastages from production.
Project #2: Installation of 3 Tons Magnet on EOT crane. (Jan 2019- July 2019)
This project was about installing magnets on crane, to have tangible gain on cost and manpower and by discontinuing outsourced scrap removing services.
Project #3: Installations of additional roll cooling system in Bar Mill. (Oct 2019- Jul 2021 )
This project needs installation and integration of an additional pump in the existing running system to improve the life of the rolls and reduce cost/ton of TMT production.
Project #4: Installation of Festoon System for EOT crane in Bar Mill. (Feb 2021- Dec 2021)
This project was about installing magnets on crane, to have tangible gain on cost and manpower and by discontinuing outsourced scrap removing services.
Project #5 : Installation of Fire Barrier and MVWS system. ( June 2022)
This project was about installations of the Fire Barrier and MVWS system for the prevention and protection of the Electrical installations from fire hazards.
Business development:
PMP - Project Management Professional
CAPM - Certified Associate in Project Management
ISO 50001 internal auditor from TUV NORD
ISO 45001 auditor from TUV NORD