To excel in business solutions through projects conceptualization, implementation and delivery with agreed quality and within agreed schedule & budget by improvising, using new concepts & techniques, mutual support, learning & sharing ideas while constantly enhancing & updating technical, managerial and interpersonal competencies.
Responsibilities: Guru Gobind Singh Polymer Addition Project :
Construction of polypropylene unit up to commissioning using project management techniques and best industry practices while using all relevant national and international codes, guidelines and recommendations and within applicable national and international laws.
Accomplishment : This unit was constructed and delivered at a cost of approx. ₹ 1000 Crores using approx. 0.84m man-days and seamlessly commissioned in May’ 2022, first among all contemporary units of the project under construction and has earned a profit of approx. ₹ 36.5 crores till its upstream unit DFCU was commissioned in December' 2022.
Special continuous focus was maintained for the following during the entire construction period to achieve the above.
Responsibilities : Conceptualization, planning and Project enabling works to build an integrated project comprising the following facilities at the northern coast of the Gulf of Kutch.
Accomplishments :
Responsibilities
Accomplishments
- By fine tuning MAOP (approx. 10% increase).
- By injection of drag reducing additives (approx. 15% increase)
- By adding new intermediate pump stations (approx. 25% increase)
Responsibilities :
Accomplishments
Responsibilities:
Accomplishments:
Though all the above stated responsibilities were completed to the fullest with value addition wherever possible, some of the major accomplishments are given hereunder.
i) By changing pipeline size and implemented the same saving a future differential capital cost of approx. Rs. 1100 crores and an yearly operating cost of Rs. 26 Crores during 9MMTPA capacity and Rs. 72 Crores during 18 MMTPA capacity.
ii) To avoid future additional loop line (parallel pipeline), construction problems like narrow ROU resulting in slow progress of pipeline, future construction manpower and resources and making the pipeline future ready.
iii) Additional safety measures to protect the nearby existing pipeline.
iv) Additional ROU in forests and other locations, fresh new crossing approvals.
Responsibilities and Accomplishments : A project comprising an SPM (single point mooring system) in Gulf of Kutch to unload VLCCs, an onshore Crude Oil Terminal (COT) for receipt, storage and further evacuation of crude oil, a 16.5km long offshore/onshore pipeline from the SPM to the COT and a 1017km long crude oil pipeline for transportation of crude oil from the COT to the proposed refinery at Bathinda.
349 Km long Vishakhapattnam - Vijaywada Multi-Product Pipeline.
Responsibilities and Accomplishments :
Pipeline Operations
Pipeline Construction
Learnings & Accomplishments:
Business Solutions through Projects