Dynamic Project Manager with extensive experience at KPMG India and Tata Consulting Engineers Limited, adept in Construction Management and Quality Assurance. Proven track record in delivering complex projects on time, enhancing workflow efficiency, and driving business development initiatives. Skilled in resource mobilization and technical problem resolution, ensuring compliance with global standards while fostering strong vendor relationships.

Overview

17
17
years of professional experience
1
1
Certification

Work History

Project Manager

KPMG India
Mumbai
04.2023 - Current
  • Has been leading Project Monitoring Office (PMO) for the Client (M/s JSW Neo Energy Ltd. ) at Site which is a 422 MW Wind turbine plant. The key responsibilities are:
    1) Responsible for Engagement Deliverables like Chairman Review Meeting (CRM),
    Management Exception Reports (MER), Site Flash Reports, etc.
    2) Complying with Global Quality and Risk Management Procedures and responsible for
    maintenance of Quality Process Review (QPR) documentation
    3) Assisting/Leading in Business Development initiatives like preparation of proposals,
    submission of bid documents against tenders, preparation of Case Studies, etc
    4) Preparation of daily review meetings, Catch up Plans, Schedule for Balance to Complete
    Jobs, Pending Jobs list, Material Follow-up

Senior Manager – Mechanical

TATA Consulting Engineers Limited
Lanjigarh
05.2021 - 04.2023
  • Delivered operational excellence services to Vedanta Limited in Lanjigarh, India.
  • Executed refurbishment of tanks and support structures, overhauling pumps, valves, and gears.
  • Reviewed work method statements, welding procedure specifications, and material test certificates.
  • Conducted feasibility analysis on construction, assessing available materials and drawings.
  • Collaborated with design department to resolve piping modifications and technical field issues.
  • Evaluated erection and dismantling methodologies, ensuring safety before heavy lifts through job safety analysis.
  • Certified contractor bills while validating extra claims for accuracy.
  • Removed bottlenecks to enhance workflow efficiency.

Manager – Mechanical

TATA Consulting Engineers Limited
Kolkata
02.2020 - 04.2021
  • Responsible for delivering the MEP works (HVAC, FPS, Plumbing, FA and PA system) for a 525 nos. sitting capacity PEB and ensuring timely completion.
  • Responsible for commissioning and handing over of all MEP systems.
  • Ensuring and driving the contractor team to adhere to the project Safety System in all aspect during project execution period.
  • Reviewing and managing project schedule by ensuring availability of materials and resources for the smooth flow of the project.
  • Certification of contractor’s bill, validating of extra quantities and claims as per contractual documents.
  • Co-ordination with design consultants for timely resolution of technical issues and drawings.
  • Tracking and managing progress and communicating the gaps if any to the contractor as per the contractual terms in order to ensure smooth flow of work.
  • Updating the project team on weekly basis and reporting the hindrance if any and its attribute to the concern team.
  • Preparing root cause analysis for slippages and non-conformances and identifying mitigation measures.
  • Devising process improvements and integration with system.

Manager – Mechanical

TATA Consulting Engineers Limited
Bengaluru
12.2016 - 01.2020
  • Responsible for delivering the MEP works (HVAC and UFAD, FPS, Plumbing, Elevators, DG, STP and WTP plant) for all buildings and ensuring timely completion.
  • Responsible for Delivering mechanical works for a Fast track IT building with 1500 Sqm floor area with 155 seating capacity in a record duration of 75 days.
  • Ensuring and driving the contractor team to adhere to the project Safety System in all aspect during project execution period.
  • Reviewing and managing project schedule by ensuring availably of materials and resources for the smooth flow of the project.
  • Adhering to the Quality assurance plan, ITP of the project in delivering the set targeted quality and ensuring.
  • Tracking of the progress and communicating the gaps if any to the contractor as per the contractual terms in order to ensure smooth flow of work.
  • Validating the variation quantities of the various components of the project wrt contractual documents.
  • Updating the project team on weekly basis and reporting the hindrance if any and its attribute to the concern team.
  • Preparing root cause analysis for slippages and non-conformances and identifying mitigation measures.
  • Devising process improvements and integration with system.
  • INDEPENDENTLY DELIVERED A FULL SCALE UNDERFLOOR AC SYSTEM IN ODC FOR THE FIRST TIME IN INDIA FOR AN AREA OF OVER 25000 SFT IN BLOCK-4 ALONE

Assistant Manager – Mechanical

TATA Consulting Engineers Limited
Jamshedpur
03.2013 - 11.2016
  • Refurbishment of old waste gas ESP. Erection and commissioning of MIGI type ESP at Sinter plant. Erection of related ducting, dampers, ID Fan & Stack, dust conveying system and compressed air system.
  • Erection & Commissioning of HVAC system for the MCC building.
  • To coordinate for the shutdown activities of Off plot and On plot tie in ducting works including shut down plan preparation, man power, machinery, shut down materials and equipment estimation, coordination for the Permit To Work procedure with client, coordination for the site preparation etc.
  • Co-ordination with design team to develop a schematic drawing as it was a brown field project.
  • Preparing detail plan/scheduling for dismantling and erection of Air pollution control system equipment.
  • Reviewing and monitoring project schedule by using MSP and Primavera as tool.
  • Member of Pre Start up Safety Audit and review team.

Assistant Manager – Mechanical

TATA Consulting Engineers Limited
Jamshedpur
12.2013 - 02.2015
  • The project involved supervision of installation and commissioning of Rotary equipment such as ID fan, Pumps. Fabrication and erection of Mix gas lines, Coke oven gas lines and other LP pipelines. Erection and commissioning of Fire Fighting system, HVAC system, De-Dusting system.
  • Erection and testing of Mix gas lines, Coke oven gas lines, firefighting and other LP pipelines.
  • Erection and commissioning of Chiller units, AHU and piping related to the HVAC system of MRSS building.
  • Erection alignment and commissioning of rotating equipment like ID fans, Pumps, Gas mixing station. Erection of stack, ESP.
  • Co-ordination with engineering and construction and liaise with the client on detail engineering requirements.
  • Study construction feasibility analysis evaluating the available material & drawings.
  • Assist design department in solving piping modification and technical problems in the field.
  • Review of WPS, welder performance, FQAP, ITP and Material test certificates.
  • Reviewing method statement and HIRA (Hazard identification and risk assessment) before any heavy lift for safe execution.

Engineer – Mechanical

TATA Consulting Engineers Limited
Jamshedpur
10.2012 - 11.2013
  • Responsible for project planning, route selection, feasibility assessment and concept selection.
  • Pipe erection along with pipe support fabrication and erection.
  • Reviewing design layout drawings, isometric drawing, P&IDs.
  • Preparation of bill of material. Preparing piping fit up, alignment reports.
  • Conduct pressure test (hydro & pneumatic) as per isometric drawings.
  • Coordinating third party inspection, NDT test.
  • Ensure safe work handling & scheduled safety instruction.

Engineer – Mechanical

TATA Consulting Engineers Limited
Jamshedpur
11.2009 - 09.2012
  • The project involved supervision of Erection, testing and commissioning of boiler pressure parts , HP and LP piping, erection and commissioning of CW, ACW and CCW system, Fire protection system.
  • Erection, alignment and welding of pressure parts as per approved field quality plan.
  • Erection and alignment of 140MT boiler steel structure.
  • Hydro test of boiler drainable part, and LP pipelines, completion of chemical cleaning, initial firing & steam blowing.
  • Welding Knowledge of High grade steel such as T-92, P-91, P-22, T-12, etc.
  • Fabrication and erection of LP piping. Erection, alignment and commissioning of CW, ACW, CCW pumps.
  • Witnessing NDT, carrying out welder qualification test and making reports.
  • Erection, testing and commissioning of yard hydrants.
  • Counter checking by isometric/piping plan for pipe erection at correct location, orientation, alignment and plumpness.

Assistant Engineer – Mechanical

TATA Consulting Engineers Limited
Jamshedpur
09.2008 - 10.2009
  • Project involved supervision of Erection, testing and commissioning of like LP piping, erection and commissioning of CW, ACW and CCW system along with its pumps and chemical dosing system.
  • Responsible for the LP piping erection work and pipe support installation in accordance with schedule, procedure, specifications, priorities and availability of construction drawings.
  • Witnessing NDT and making reports, carrying out Welder qualification test.
  • Responsible for carrying out mechanical clearances, carrying out hydro and pneumatic tests, fulfilling commissioning and pre-commissioning requirements for the project.
  • Carrying out Final P&ID check of installed piping systems.

Education

Bachelor of Technology - Mechanical Engineering

B.C. Roy Engineering College
Durgapur, WB, India
01.2008

MBA - Marketing And Finance Management

Subharti University
Meerut

Skills

  • Construction Management
  • Project Management
  • Resource Mobilization
  • RFI Management
  • Quality Assurance
  • Cost Management
  • Quantity Surveying
  • Construction Safety
  • Scope Document Review
  • Change Management
  • Engineering Drawing Review
  • Technical Bid Clarification
  • Bill Certification
  • JSA/HIRA Review
  • Project Metrics Review
  • Quality Standards Compliance
  • Vendor Coordination
  • Technical Inputs for Construction Methodologies
  • Site Management Coordination
  • Technical Problem Resolution
  • Meeting Organization
  • Action Plan Follow-up
  • Statutory Licensing
  • Approval Tracking
  • Compliance Monitoring
  • Inspection Coordination
  • Technical Detail Clarification
  • Reporting Requirements

Certification

  • ASNT Level II in Radiographic testing
  • Welding QA & QC for Engineers (IH-QAP-1) in ADOR Institute of welding technology
  • Primavera from CADD centre training services

Personal Information

  • Date of Birth: 11/14/83
  • Nationality: Indian
  • Driving License: Indian
  • Marital Status: Married

Languages

  • English
  • Hindi
  • Bengali
  • Odia

Languages

Hindi
First Language
English
Proficient (C2)
C2
Bengali
Proficient (C2)
C2
Oria
Upper Intermediate (B2)
B2
Bhojpuri
Proficient (C2)
C2

Timeline

Project Manager

KPMG India
04.2023 - Current

Senior Manager – Mechanical

TATA Consulting Engineers Limited
05.2021 - 04.2023

Manager – Mechanical

TATA Consulting Engineers Limited
02.2020 - 04.2021

Manager – Mechanical

TATA Consulting Engineers Limited
12.2016 - 01.2020

Assistant Manager – Mechanical

TATA Consulting Engineers Limited
12.2013 - 02.2015

Assistant Manager – Mechanical

TATA Consulting Engineers Limited
03.2013 - 11.2016

Engineer – Mechanical

TATA Consulting Engineers Limited
10.2012 - 11.2013

Engineer – Mechanical

TATA Consulting Engineers Limited
11.2009 - 09.2012

Assistant Engineer – Mechanical

TATA Consulting Engineers Limited
09.2008 - 10.2009

Bachelor of Technology - Mechanical Engineering

B.C. Roy Engineering College

MBA - Marketing And Finance Management

Subharti University
Rakesh Kumar Singh