Been a part of Mission 96 tower at CIDCO project 96 flats in 96 days handing over
Been a part of Mission 96 tower at CIDCO project 96 flats in 96 days handing over
Generic
Supriya Varthe

Supriya Varthe

Civil Engineer
Mumbai

Summary

Dedicated procurement manager and professional with history of meeting company goals utilizing consistent and organized practices. Skilled in working under pressure and adapting to new situations and challenges to best enhance the organizational brand.

Overview

5
5
years of professional experience
15
15
years of post-secondary education

Work History

Procurement Manager

Larsen & Toubro Ltd
Mumbai
02.2020 - Current
  • Negotiated complex corporate procurement contracts by working closely with internal and external contacts.
  • Reviewed and issued contracts and blanket purchase orders after choosing ideal vendor and drive procurement process.
  • Developed and maintained relationships with key suppliers for smooth communication and to meet required expectations.
  • Evaluated supplier quotes based on purchasing procedures and competitiveness in quality, price and delivery.
  • Resolved conflicts and negotiated mutually beneficial agreements between parties.
  • Developed productive relationships with key account holders.

Material Coordinator

Larsen & Toubro Ltd
Mumbai
02.2020 - Current
  • Managed receiving operations and proper storage of incoming materials.
  • Worked with project managers to determine schedule and volume requirements in order to effectively coordinate deliveries and maintain supply levels.
  • Trained, motivated and instructed team of [15] employees staging and preparing items for deliveries.
  • Adhered to all safety protocols and standards when operating equipment such as inhouse crusher plant.
  • Handling day to day in and out transactions pertains to inhouse crusher plant to ensure smooth supply of bulk materials i.e aggregates, crusher sand, boulders, GSB etc. to complete daily site concreting plan leading to generation of invoice.
  • Scrutinizing and certifying bulk material suppliers and specialized crusher plant operation contractor's bill in line with contract document to facilitate their cash flow.
  • Currently handling minimum 2.5 cr monthly transactions related to bulk material operations.

Education

Post Graduate Program in Construction Management - Construction Management

NICMAR
Pune
03.2011 - 11.2019

Bachelor of Engineering - Civil Engineering

AISSMS, Collage of Engineering
Pune
06.2004 - 05.2008

Diploma in Civil Engineering - Civil Engineering

K.J.Somaiya Polytechnic
Vidyavihar,Mumbai
12.2001 - 05.2004

Skills

Purchasing, Vendor management, Negotiation skills, strong interpersonal skills

undefined

Accomplishments

Been a part of Mission 96 tower at CIDCO Mass housing project at PMAY scheme at Kharkopar, Ulwe

Work Availability

monday
tuesday
wednesday
thursday
friday
saturday
sunday
morning
afternoon
evening
swipe to browse

Timeline

Procurement Manager

Larsen & Toubro Ltd
02.2020 - Current

Material Coordinator

Larsen & Toubro Ltd
02.2020 - Current

Post Graduate Program in Construction Management - Construction Management

NICMAR
03.2011 - 11.2019

Bachelor of Engineering - Civil Engineering

AISSMS, Collage of Engineering
06.2004 - 05.2008

Diploma in Civil Engineering - Civil Engineering

K.J.Somaiya Polytechnic
12.2001 - 05.2004

Been a part of Mission 96 tower at CIDCO project 96 flats in 96 days handing over

*Mission 96 tower means 96 apartment in 96 days. i.e per day one apartment.

*It's a G+12 story tower built in precast technology where a total of 1,985 precast elements of the superstructure were assembled over a built-up area of 64,000 sq. ft.

*96 apartments including all finishes completed with lock and key position.

Been a part of Mission 96 tower at CIDCO project 96 flats in 96 days handing over

*Mission 96 tower means 96 apartment in 96 days. i.e per day one apartment.

*It's a G+12 story tower built in precast technology where a total of 1,985 precast elements of the superstructure were assembled over a built-up area of 64,000 sq. ft.

*96 apartments including all finishes completed with lock and key position.