CV B.E (Civil), M.B.A (project management), M.Tech (Environmental engineering) with 17+ years of experience in various fields in civil, Water and Wastewater engineering & Project Management. Aspiration To be the best in any field I am in , with the growth and sustainability of the firm which I am working for. Hardworking professional civil engineer Specialist familiar with project management knowledgeable about Water, Wastewater engineering and Fecal sludge management requirements. Fluency in English, Tamil Kannada and Hindi
I. Project details:
a) Working as Senior associate (Engineering) under City Wide Inclusive Sanitation project – Trichy city.
II. Activities performed :
a) Lead the Engineering team under City- wide inclusive sanitation, Trichy hub and supported the state level team to deliver the Fecal sludge management related implementation.
b) Assessing the sanitation related issues at the selected ULB’s in Tamilnadu. And provide a technology options to improve the sanitation condition of the city on the Fecal sludge management including Co treatment.
c) Providing technical support and Conduct pilot demonstration on the improved services for infrastructures such as Sewage treatment facilities, Sewage pumping stations and decanting stations at the city.
d) Closely working with City corporation and the State technical support team of Commissionerate of Municipal Administration on the improvements in selective Sustainable Development Goals.
e) Practicing of the sanitation improvements to develop the public health in terms of Fecal oral transmissions and sanitation workers safety.
f) Stake holder management
I. Project details:
a) Worked as Construction manager (planning) for APCRDA LPS packages for 3 zones
II. Activities performed :
a) Lead the planning team
b) Responsible for project scheduling, invoicing, resource planning and allocation.
c) Sub-contractor management
d) Internal project monitoring and controlling
e) Material resource planning and allocation
f) Daily, Weekly and Monthly progress report to client as well internal
I. Project details:
a) Worked as Construction Engineer for Construction and supervision part of PMC service for Construction of 300mld WTP and refurbishment of existing 300mld WTP.
b) Worked as Support Construction Engineer for Construction and supervision part of Replacement and Rehabilitation of existing Sewer System in Virushabhavathi Valley, Bangalore (RCC NP3 pipes of various dia meters from 400 mm to 2200 mm – 18.9 km).
c) Worked as Support Design Engineer for
i. Design part of Slum Development Component- Implementation of Water Supply and Sanitation Facilities to all Slums in Bangalore
ii. Design part of Replacement and Rehabilitation of existing Sewer System in Virushabhavathi Valley, Bangalore.
d) Worked as Support Construction Engineer
i. Construction and supervision part of Construction of GLR of 24 MLD capacity at uttarahalli, Bangalore
ii. Construction and supervision part of Construction of GLR of 18 MLD capacity at Jambu Savari dinne, Bangalore
II. Activities performed :
Ø Responsible for Overall supervision of the construction activity and implementation of work as per design and specification
Ø Responsible for Shorting out of technical issues in site immediately
Ø Sharing technical ideas with client and contractor.
Ø Monitoring Quality Control, quality assurance & safety at site
Ø Overall implementation of Quality Standards at site
Ø Overall control of documentation and billing part of entire project work with respect to QA/QC aspects
Ø Co-ordination with Design Engineers/Contractors & Clients
Ø Planning /monitoring of works & construction methods in site
Ø Progress Monitoring/attending Progress Review Meetings
Ø Preparing Progress Report at site.
Ø Sewer line networking using sewer cad & Site visit and collecting of design
Ø Co- coordinating to Preparation of design reports & cost estimates
Ø Co- coordinating to Preparation of BID documents & Technical / Financial Evaluation
Ø Technical co-ordination with clients and contractor as a consulting engineer in all activities
I. Project details:
Worked as a Site In charge for
a) Construction of G+4 building at virugambakkam, Chennai, Tamilnadu.
b) Construction of compound wall, preparation of gardening work, Commissioning of water and sanitary connections to the whole apartments (9 buildings each having 32 flats), Road works around the Buildings at virugambakkam, Chennai, Tamilnadu.
c) In charge for 2 No’s of G+4 buildings at maduravayel, Chennai, Tamilnadu.
II. Activities performed:
Ø Construction engineering & quality control of civil works
Ø Construction of G+4 building at virugambakkam, Chennai, Tamilnadu.
Ø Construction of compound wall, preparation of gardening work, Commissioning of water and sanitary connections to the whole apartments (9 buildings each having 32 flats), Road works around the Buildings at virugampakkam, Chennai, Tamilnadu.
Ø 2 No’s of G+4 buildings at maduraivayel (32 flats X 2 Buildings), Chennai, Tamilnadu.
Ø Co-ordination with Design Engineers, interdisciplinary teams & Client.
Ø Planning & monitoring of works & construction methods.
Ø Progress Monitoring, attending Progress Review Meetings and Preparing Progress Report etc.
Ø Preparing and attending the Weekly Quality meeting.
Ø Quantity surveying, Monitoring Safety aspect.
Ø Project Planning, Cost controlling & estimation.
I. Project details:
Worked as a Site Engineer for
a) Construction of various capacities of overhead tanks, Ground Level Reservoirs and pipe line laying at Rameshwaram, Tamilnadu. Capacity from 40K ltr to 2 ML(Kavery Water supply to Rameshwaram)
b) Construction of 6L ltr Capacity wet well near Thirumoorthy Hill Dam, Udumalaipet, and Tamilnadu. (Madathukulam Water supply).
c) Construction of 13.75MLD capacity Water Treatment Plant near Thirumoorthy Hill Dam, Udumalaipet, Tamilnadu. (Madathukulam Water supply).
d) Construction of 12L lit capacity OHT in Tamilnadu.(Madathukulam Water supply)
e) Additional work in-charge for Construction of pipe carrying bridge near Pillur Water Treatment Plant in Tamilnadu. (Pillur Water supply scheme)
II. Activities performed:
Ø Site execution, Cost control, labour management and material management.
Ø Co-ordination with Design Engineers, interdisciplinary teams & Client.
Ø Weekly labour billing and all the management activities at site.
Ø Monthly RA Bill preparation and submission to client for approval.
Ø Planning, monitoring of works & construction methods.
Ø Progress Monitoring, attending Progress Review Meetings and Preparing Progress Report etc.
Ø Quantity surveying, Monitoring Safety aspect.
Ø Project Planning, Cost controlling & estimation.
Ø Monitoring Quality Control, quality assurance & safety at site.
Ø Implementing new construction methods.
Full site management activities done, directly reported to Managing director