Dynamic Project Lead with extensive experience at Expertise Contracting Company Ltd, adept at resource allocation and project management. Proven track record in leading large teams, ensuring safe execution of complex projects, and enhancing operational efficiency. Skilled in client communications and mentoring, driving successful outcomes in high-stakes environments.
Lead a team of 50 for Removal ,Overhauling and Installation of Seawater Pumps and Cooling water pumps including demolition and construction of new foundation in a Sabic Affliate Saudi Arabia
Incharge for resource planning like manpower,spares,materials and temporary facilities inside the plant
Coordination with client for PSSR,Precommissioning and Commissioning activities
Responsible for Safe Execution of all activities inside the plant
Responsible for Training subordinates
Lead a team of 120 for Rotating Equipment, Valves and Heat Exchanger Maintenance and Construction services
Worked as Project Manager in many MOC projects in Sabic Affliates in Saudi Arabia
Have done Turnaround Projects in Sabic Affliates and Aramco
Incharge for the Maintenance workshop
Assisting Estimation team for technical requirements
Incharge for Manpower, Materials planning
Responsible for annual budgeting of the department
Have done Overhauling, Installation and Erection of Pumps of various sizes and types,Centrifugal compressors,Steam Turbines,Gearboxes,Valves and Heat Exchangers etc.
Responsible for training of subordinates
Erection and Installation of Pumps,Compressors,Steam Turbines,Centrifugal Compressors,Reciprocating Compressors,Finfan Coolers etc.
Incharge for precommissioning activities like Motor Solorun,Turbines Solorun,Final alignment,Oil Flushing
Commissioning of all Rotating Equipments
Coordinating with client for Mechanical completion walkdowns,PSSR and plant handover
Preservation of all Rotating Equipments
Overhauling and Maintenance of Rotating Equipments based on the requirements
Coordinating with EPC for Installation and Erection of Rotating Equipments like Pumps,Centrifugal compressor,Reciprocating Compressors,Steam Turbines,Reactors,Finfan coolers,Agitators etc
Conducting Mechanical Completion walkdowns
Conducting PSSR walkdowns
Preservation of Equipments
Overhauling and Maintenance of Equipments
Preperation of SPIR
Conducted Job Qualification Program for all technicians
Overhauling and Maintenance of Equipments Monomer and Utilities department
Have worked in Plant expansion project
Constructed new Cooling water system with Cooling towers, Cooling water Pumps and Pipings
Constructed new Chilled water system( 500 TR capacity) with new Compressors,Coolers and Chillers
Erected and Installed Poly Reactors with Agitator
Maintaining Spareparts inventory in workshop
Overhauling and Maintenance of all Rotating and Static Equipments in Polymer section
Maintaining spareparts inventory
Preventive Maintenance of Equipments
Attending Breakdowns in Plant
Training of subordinates
Erection of all Equipments in the plant
Overhauling and Maintenance of Equipments in the plant
Project management