Summary
Overview
Work History
Education
Skills
Additional Information
Timeline
Generic

Debabrata Adhikari

Deputy Manager-QA/QC
Purulia,India

Summary

Quality professional with about 10.0 years of experience in the construction of underground metro projects by both top-down and bottom- up construction methodology in major Underground Metro Projects in India. Worked with tunnel by TBM and NATM both method. Worked at Casting yard.

Overview

10
10
years of professional experience
3
3
years of post-secondary education
3
3
Languages

Work History

Deputy Manager-Casting Yard

Gukermak-Sam India JV/ Kanpur Underground Metro Project/ KNPCC-05
Kanpur, India
02.2023 - Current


Working currently with Gulermak-Sam India for the Design and Construction of underground metro works at Kanpur Metro underground KNPCC-05 project including four underground station and ramp .

4 underground stations, 5.5 km Tunnel (TBM).

  • Timely completion of ring casting.
  • Minimize time cycle to get maximum production per day per mold.
  • Meeting daily requirement of fixtures by tracking consumption and vailability.
  • Inspection of the mold dimension, Cages and steam curing.
  • Verify correct / approved materials are utilized for the works carried out.
  • Ensure fulfillment of all inspection & test requirements at all stages as per ITP, Specification & contract requirements.
  • In-processes and Final Inspection of all civil / structural jobs carried out at the site in coordination with client, consultant/Third Party Inspectors.
  • To provide Toolbox training on a daily basis & Quality Induction training for new workers.

Assistant Manager

Afcons-Sam India JV/ Agra Underground Metro Project/ AGCC-02
Agra, India
08.2022 - 01.2023
  • Ensure stage-wise inspection of all the works are carried out at site as per approved drawing and methodology and getting final conformance approval from the client/consultant.
  • Verify correct / approved materials are utilized for the works carried out and necessary test certificates.
  • Ensuring post-pour inspection of works and necessary arrangements for curing, finishing, and repairing, etc.
  • To control & analyze non-conformity and observation, if any, pertaining to the system and ensures its implementation and effectiveness of the corrective action taken and compliance reports prepared within the stipulated time frame.
  • Aimed at waterproofing work for roof slab and drainage system.
  • Material Source approval from client
  • Vendor approval for different permanent structure materials

Senior Engineer- QA/QC

Tata Projects Ltd/ Pune Underground Metro Projects/UGC-01 & 02
Pune, India
11.2019 - 07.2022

5 underground stations, 6.0 km Tunnel (TBM and NATM).

Worked with Tata Projects Ltd., India for the Design and Construction of underground metro works at Pune Metro underground UGC-01 & UGC-02 project from agricultural college to northern end of Budhwarpeth station.

  • Ensure implementation of all QA/QC Procedures, QC Plans, and Work Instructions in accordance with Organization’s Quality System Manual.
  • Verify correct / approved materials are utilized for the works carried out and necessary test certificates.
  • Ensuring post-pour inspection of works and necessary arrangements for curing, finishing, and repairing, etc.
  • To control & analyze non-conformity and observation, if any, pertaining to the system and ensures its implementation and effectiveness of the corrective action taken and compliance reports prepared within the stipulated time frame.
  • Aimed at waterproofing work for roof slab and drainage system.
  • Tunnel by TBM daily inspection
  • NATM method tunnel daily inspection and tests perform

Engineer-QA/QC

Tata Projects Ltd/ Lucknow Metro Project/ LKCC-06
Lucknow, India
06.2016 - 10.2019

3 underground stations, 3.5 km tunnel.

Design and construction of underground metro works at Lucknow Metro underground LKCC-06 project from underground ramp near Charbagh metro station to ramp near K.D. Singh Babu stadium station.

  • Ensure stage-wise inspection of all the works are carried out at site as per approved drawing and methodology and getting final conformance approval from the client/consultant.
  • Verify correct / approved materials are utilized for the works carried out and necessary test certificates.
  • Gained strong leadership skills by managing projects from start to finish.
  • Ensuring post-pour inspection of works and necessary arrangements for curing, finishing, and repairing, etc.
  • To control & analyze non-conformity and observation, if any, pertaining to the system and ensures its implementation and effectiveness of the corrective action taken and compliance reports prepared within the stipulated time frame.
  • Aimed at waterproofing work for roof slab and drainage system.
  • Worked effectively in fast-paced environments.

Engineer-Civil

Larsen & Toubro- Construction/ Chennai Metro Projects/
Chennai, India
12.2015 - 06.2016

Design and construction of 4 nos underground station, Ramp, and cross passage by top-down method

04 underground stations, 4 Ancillary buildings, 16 Entrance & 9 Cross Passages

  • Ensure stage-wise inspection of all the works are carried out at site as per approved drawing and methodology and getting final conformance approval from the client/consultant.
  • Verify correct / approved materials are utilized for the works carried out and necessary test certificates.
  • Ensuring post-pour inspection of works and necessary arrangements for curing, finishing, and repairing, etc.
  • To control & analyze non-conformity and observation, if any, pertaining to the system and ensures its implementation and effectiveness of the corrective action taken and compliance reports prepared within the stipulated time frame.
  • Checking of all the quality parameters as per the Inspection Test Plan of Bentonite Slurry and concrete before pouring.
  • Discussion with execution team to minimize non-conformance and prepare compliances of the same.

Engineer-Civil

Larsen & Toubro Construction/ Delhi Metro Projects/CC-05
Delhi, India
08.2013 - 12.2015

03 underground stations, and 5.7 km tunnel (TBM & NATM) & 4 Cross Passages.

Design and Construction of Tunnel by Shield TBM and ITO, Delhi Gate, Jama Masjid Station & Mandi House Launching shaft by top-down & Bottom-up Method of phase -3, CC-05

  • All kinds of in-house and third-party testing related to raw materials (i.e., cement, aggregate, water, admixture, etc.), fresh and hardened concrete, and maintaining its records.
  • To collect and compile all the material testing certificates for various construction materials used in the project.
  • Ensure maintenance of calibration records of equipment used at a laboratory.
  • Preparing daily, weekly, and monthly quality reports, preparing a master file for work/activity monitoring, ITP sign’s off.
  • Execution and installation of fire sealant and fire doors in stations.
  • Execution of waterproofing work and CJ treatment

Education

Matriculation -

Chittaranjan High School
Purulia
04.2001 -

Diploma in Civil Engineering - Civil Engineering

Purulia Polytechnic
Purulia
05.2010 - 06.2013

Skills

    Quality Management System

undefined

Additional Information

Achievements:

  • Successfully completed DMRC-CC-05 Project before time and handed over ITO Station.
  • Successfully completed LKCC-06 Project before time and handed over Hussainganj, Sachivalaya & HazratGanj Station Before time .
  • Awarded with best performer in the field of QA/QC by GTJV for the year of 2016-2017.
  • Recognized for the timely completion of TBM work without any major Quality related issues in Pune Metro Projects

Timeline

Deputy Manager-Casting Yard

Gukermak-Sam India JV/ Kanpur Underground Metro Project/ KNPCC-05
02.2023 - Current

Assistant Manager

Afcons-Sam India JV/ Agra Underground Metro Project/ AGCC-02
08.2022 - 01.2023

Senior Engineer- QA/QC

Tata Projects Ltd/ Pune Underground Metro Projects/UGC-01 & 02
11.2019 - 07.2022

Engineer-QA/QC

Tata Projects Ltd/ Lucknow Metro Project/ LKCC-06
06.2016 - 10.2019

Engineer-Civil

Larsen & Toubro- Construction/ Chennai Metro Projects/
12.2015 - 06.2016

Engineer-Civil

Larsen & Toubro Construction/ Delhi Metro Projects/CC-05
08.2013 - 12.2015

Diploma in Civil Engineering - Civil Engineering

Purulia Polytechnic
05.2010 - 06.2013

Matriculation -

Chittaranjan High School
04.2001 -
Debabrata AdhikariDeputy Manager-QA/QC