I was looking after overall aspects of infrastructure operations related to Data Center including Electrical Setup (HT/LT panels, Switchyards, Dry and Oil Transformers , Generators , UPS , Battery Banks , PDU , Fire Fighting setup (FAS , VESDA , NOVEC) Mechanical Setup ( Chillers, CRAH, AHU,Pumps , Cooling Towers ) and related BMS systems
KEY RESPONSIBILITIES:
- Preparation of power consumption reports i.e monthly reports.
- Prepare site audit documentation on quaterly basis .
- Skilled at analyzing and interpreting information
- Conduct weekly meetings with Colo engineering team members to review progress on projects and identify areas needing improvement
- Prepare documentation on monthly basis for our PM also ensure to complete all the PM within SLA.
- Performed regular inspections of facilities and equipment used in the engineering process to ensure safe working conditions
- Update reports(PM tracker , highlights lowlights,power comsumption on weekly basis
- Investigation on root causes for operation issues and developed appropriate corrective actions
- Maintenance of HT/LT electrical system,DG,fire Alarm system,VESDA,BMS control etc.
- Maintenance Adhered to timelines to meet quality assurance targets
- Safety and HouseKeeping at workplace looked after DG , Air Conditioning Systems , PDU , Transformers , HVAC.
- Use to take care of finance related actions.
- Maintain the records of EOSL , FSB , critical spares ,unplanned incident tracker.
- Check ATS , breaker healthiness on regular basis.
- Review FAT reports
- Review action items from different sites and prepare deck on monthly basis
- Maintain PUE in every POD
- Review thermography reports and plan the activity as per report
- vendor management of PM activities
PROJECT HANDLE:
- Valuable contribution to successful completion PM of oil filtration , transformer testing on 70 MVA transformer without disturbing the downstream power.
- Valuable contribution to successfully completion of DG alternation testing on our 22 no of DGs.
- Successfully completion of rack infill project.
- Successfully completion of providing external source to USB control power.
- Disable the cross feeds of the primary and catcher at USB panels.