I have more than 7 Years of experience Including 10 Turnaround As a Project & Maintenance Engineer achieving successful progress of various activities, Ranging from Project planning, Shutdown jobs from pre-shutdown activities to job handover to clients, Project Execution, Managing documentation of all information related to the projects in Oil & Gas Industries & Oil Refineries
Turnaround of Asab AGP-0 & Asab AGP-2 (2022)
Turnaround of Asab AGP-1 & Asab AGP-2 (2023)
• Accepting job permits from the client representative as PA.
• Responsible for all aspects of the day-to-day maintenance activities of Static equipment in terms of safety, quality and in timely manner.
• Understand the scope of work and coordinates with the different disciplines in order to mitigate the interference/clashes.
• Coordinating with the design engineers at the engineering stage in order to mitigate/avoid the hazards & risks during erection activities.
• Supervise the progress and performance of the erection and Maintenance crew in order to ensure the productivity, quality and standards are maintained.
• Carrying out the HSE & quality weekly walk through to make sure the standards are followed and maintained.
• Responsible for carrying out mechanical clearance for erection and maintenance of static, rotary equipment and clear it from quality inspection.
• Ensure that all punch lists are resolved for handover is satisfactorily concluded and that there is no prolongation of project.
• Ensure labor force allocated on the job is productively used.
• Maintenance and inspection of rotary and static equipment.
• Maintain Daily report also and distribute job to worker.
• Supervise and execute the prevention, corrective maintenance of static equipment like vassal, heat-exchanger, reactor’s, fin-fan and valves etc.
• Maintenance of the plant and equipment’s by planning schedule
• All maintenance work carried out under safety and work permit system.
• Understand the P&ID and Isometric detail & specification drawing.
• Supervising team of local Personnel and being involved in the whole Activates of shutdown/Turnaround.
• Done Pre shutdown and Shutdown Activity.
Project Name: Shutdown Maintenance.
Client Name:CPCL Chennai india.
• Responsible for all aspects of the day-to-day maintenance activities of Static equipment in terms of safety, quality and in timely manner.
• Understand the scope of work and coordinates with the different disciplines in order to mitigate the interference/clashes.
• Coordinating with the design engineers at the engineering stage in order to mitigate/avoid the hazards & risks during erection activities.
• Supervise the progress and performance of the erection and Maintenance crew in order to ensure the productivity, quality and standards are maintained.
• Carrying out the HSE & quality weekly walk through to make sure the standards are followed and maintained.
• Responsible for carrying out mechanical clearance for erection and maintenance of static equipment and clear it from quality inspection.
• Ensure that all punch lists are resolved for handover is satisfactorily concluded and that there is no prolongation of project.
• Ensure labor force allocated on the job is productively used.
• Tool box talk given before starting the work about safety and quality.
• Coordinating with the workload and distribute the work amongst the worker.
• Supervising maintenance job of heat exchanger, fin fan cooler and isolation job.
• Ensuring that inspection requests are implemented.
• Accepting job permits from the client representative
• Verify that all applicable equipment is calibrated and has valid certification
• Monitoring that work is being carried out safely &securely, maintaining safe Work practices.
Project Name: Mechanical Maintenance Job Turnaround Shutdown
Client Name: Saudi Aramco refinery (PETRO RABIGH).
• Responsible for all aspects of the day-to-day maintenance activities of Static equipment in terms of safety, quality and in timely manner.
• Understand the scope of work and coordinates with the different disciplines in order to mitigate the interference/clashes.
• Coordinating with the design engineers at the engineering stage in order to mitigate/avoid the hazards & risks during erection activities.
• Supervise the progress and performance of the erection and Maintenance crew in order to ensure the productivity, quality and standards are maintained.
• Carrying out the HSE & quality weekly walk through to make sure the standards are followed and maintained.
• Responsible for carrying out mechanical clearance for erection and maintenance of static equipment and clear it from quality inspection.
• Ensure that all punch lists are resolved for handover is satisfactorily concluded and that there is no prolongation of project.
• Ensure labor force allocated on the job is productively used.
• Maintenance and inspection of static equipment.
• Maintain Daily report also and distribute job to worker.
• Supervise and execute the preventive, corrective maintenance of rotary Equipment like pump, fan, blower, compressor and turbine.
• Supervise and execute the prevention, corrective maintenance of static equipment like vassal, heat-exchanger, reactor’s, fin-fan and valves, columns etc.
• Maintenance of the plant and equipment’s by planning schedule
• All maintenance work carried out under safety and work permit system.
• Understand the P&ID and Isometric detail & specification drawing.
• Supervising team of local Personnel and being involved in the whole Activates of shutdown/Turnaround.
• Done Pre shutdown and Shutdown Activity.
Clint Name: Essar, IOCL & BPCL
Project Name: Shutdown Job.
• Maintenance and inspection of rotary and static equipment.
• Maintain Daily report also and distribute job to worker.
• Supervise and execute the preventive, corrective maintenance of rotary Equipment like pump, fan, blower, compressor and turbine.
• Supervise and execute the prevention, corrective maintenance of static equipment like vassal, heat-exchanger, reactor’s, fin-fan and valves etc.
• Maintenance of the plant and equipment’s by planning schedule
• All maintenance work carried out under safety and work permit system.
• Understand the P&ID and Isometric detail & specification drawing.
• Supervising team of local Personnel and being involved in the whole Activates of shutdown/Turnaround.
• Done Pre shutdown and Shutdown Activity.
Project Name: Mechanical Maintenance Job Shutdown activity.
Client Name: Petrokemya Jubail (KSA), Al-Razi, YASREF Yanbu, Saudi ARAMCO Ras-al-khair & Maaden Phosphate company.
• Responsible for all aspects of the day-to-day maintenance activities of Static equipment in terms of safety, quality and in timely manner.
• Understand the scope of work and coordinates with the different disciplines in order to mitigate the interference/clashes.
• Coordinating with the design engineers at the engineering stage in order to mitigate/avoid the hazards & risks during erection activities.
• Supervise the progress and performance of the erection and Maintenance crew in order to ensure the productivity, quality and standards are maintained.
• Carrying out the HSE & quality weekly walk through to make sure the standards are followed and maintained.
• Responsible for carrying out mechanical clearance for erection and maintenance of static, rotary equipment and clear it from quality inspection.
• Ensure that all punch lists are resolved for handover is satisfactorily concluded and that there is no prolongation of project.
• Ensure labor force allocated on the job is productively used.
• During this period, I done several shutdowns for Company as Mechanical maintenance supervisor & Site Incharge.
• Tool box talk given before starting the work about safety and quality.
• Coordinating with the workload and distribute the work amongst the worker.
• Supervising maintenance job of heat exchanger, fin fan cooler and isolation job.
• Ensuring that inspection requests are implemented.
• Accepting job permits from the client representative
• Verify that all applicable equipment is calibrated and has valid
certification
• Monitoring that work is being carried out safely &securely, maintaining safe Work practices.
Project Name: Pre-Shutdown and shutdown Maintenance.
Client Name: Reliance Jamnagar, IOCL Vadodara, IPCL Vadodara, IOCL Bhatinda,BPCL Mathura etc.
• Supervise and execute the prevention, corrective maintenance of static equipment like vassal, heat-exchanger, reactor’s, fin-fan, column and valves etc.
• Maintenance of the plant and equipment’s by planning schedule.
Clint Name: Reliance Vadodara IPCL.
Planning and Coordination
WMS Certified as PA in Adnoc Gas processing
WMS Certified as PA in Adnoc Gas processing
Primavera P6