Civil Engineer; accomplished construction professional offering more than 14+ year of experience.
Client: Public work department, DIU
Project-19: Protection and Construction of Passive and Active supports for remaining Zones at Naida Cave , Diu
Project-18: Construction Of Passive Support System - Individual columnar support for Zone 1 & 3 at Naida Cave, Diu.
• Protection of Cave from rock fall. Total 15 zone with active and passive supports.
• Active support of rock bolting, rock gluing and Shotcreting.
• Passive support is Make RCC structure for support the rock.
Project-17: Construction of Infinity Swimming Pool at Jhalander Beach Circuit House, Diu.
• A VVIP swimming pool of 380 Sq.Mtr area.
Project & Billing Engineer Client: Diu Smart City Ltd., DIU.
Project-16: Construction of Jethibai Bus Terminal and Area Development of Old Fish Market with Defect and Maintenance Liability for Five Years under Smart City Mission at Diu.
Project & Billing Engineer
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav (2022-ongoing)
Project-15: Restoration of existing shiyalbet bunds impacted and damaged by cyclone Tauktae.
• Maintaining stock yard for rock segregation.
• Three Category of armor rock Secondary 60-300 kg, Primary-01=150-600 kg , Primary-02= 500-1500Kg.
• Bund profiling, laying of armor rock for.
• Construction of Rock Revetment work for700 m Seaside & leeside.
Client: Public work department DIU
Project-14: Development of lNS Khukri Memorials Hill at Chakratirth Beach, Diu. (2019-2021)
• Iconic project in Diu, known as Sunset Point of Diu.
• Constructed the most beautiful sea face amphitheater (open theater) finished with granite and artificial turf.
• Green rooms and panel room, utility room etc.
• Glass Model Room with laminated glass with etching of 10mm+1.52 +10mm plain laminated glass.
• Khukri ship model using Oke wood, Pine, teakwood and waterproof marine ply.
• Restoration of old temple.
• Development of garden for 6000 sq.mt with shrubbery & tree plantation.
• Pump House with fully automatic machinery, and pumping equipment’s and drip irrigation system.
• Finishing pathway with side wall masonry, plaster, RCC and make base of filling material and base concrete and finishing with Granite on all expose wall and pathway.
• Electrification for the entire project with international luminaries, with necessary cabling piping, panel room, switches etc.
• Installation of International brand CCTV Camera and necessary attachment for operation.
Project-13: 50 mtr pile jetty at Vanakbara, DIU (2018-2019)
• Fishing jetty with 30 pile of 1000 mm dia for a depth of 21.5 mtr.
• Precast erection work pile muff, RCC beam, Slab, RCC platform of 50X40 mtr.
• Utility piping for drainage etc.
• RCC platform 2500 sq.mt.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav (2017-2018)
Project-12: Concrete Superstructure for container scanner at APM terminals Pipavav
• Civil structure for container scanner with machine room RCC wall of 6 mtr height paver road.
• Weight Bridge foundation, pipe ducting, electrical foundation.
Client: Public work department DIU
Project-11: Construction of pile jetty for a length of 92.00 Mts. At Vanakbara Diu(2016-17)
• 54 land piles of 1.00mtr dia of 21 mtr Depth.
• Cast in-situ Pile Jetty Of 92.00X12.5 Mtr with Precast Pile Muff, precast beam and pre cast slab.
• RCC platform of 95X47 mtr.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-10: Container yard extension work (Work with man infra structure ltd.)(2016-2017)
• 13 RTGC Tracks and 3 trench drain of length 300 mtr.
• Develop area of 300X300 mtr. Including Industrial Foundation like Electrical Draw Pits & Ducting, Transformer Foundation, High Mast, Fire Hydrants, fire line, collection pits and GRP pipe lines etc.
• Prepare the base for yard with CBM & CBGM Concrete almost 56000 cu.m.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-9: Supply of Precast Concrete Block of 1.6M., 2.4M., 3M., 5M. &6M. (Work with Conductix Wampfler India Pvt. Ltd.)(2016-2017)
• 582nos of M-40 grade concrete blocks of particular length- 1.6 mtr, 2.4 mtr, 3Mtr, 5Mtr &6 mtr.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-8: Sewage Treatment Plant 750KLD including Pipe network (2015-2016)
• Execution of Site as Per AFC drawing above ground.
• Preparing measurement sheets and BBS and maintain daily progress report.
Client: Gujarat Guardian Ltd. / Sterling & Wilson Ltd.
Project-7: Const. of Drain gabion wall RCC road and collection pit for GGL(2015-16)
• Under Ground Collection Pits of Size 9X8X6 &14.5X9.5X7 mtr.
• RCC Strom Water drain Of Length 700 mtr & Trapezoidal Stone Pitching Drain Of 500 mtr.
• Draw Pits Of 4X4X4 Mtr 7 nos. and RCC Culverts And Roads etc.
• Gabion structure of 1.5 mtr Width& 700 mtr Length with Turfing.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-6: 1 bhk apartment pile foundation (2014-15)
• Execution of foundation work of 5 nos. of 1bhk apartment.
• Maximum load capacity of one pile is 47.5 MT
• Total no. of pile: 440 depth of pile 12 mtr and diameter 450mm.
• Project is up to plinth level with pile cap.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-5: Club House Building pile& Pile Cap foundation (MOU with Barrad & Duggle Pvt Ltd)(2014-15)
• Execution of foundation work of all sites.
• Maximum load capacity of one pile is 47.5 MT
• Total no. of pile: 424 depth of pile 12 mtr and diameter 450mm.
• Project is up to plinth level with pile cap.
Client: APM Terminals (Gujarat Pipavav Port Ltd) Pipavav
Project-4: Construction Monsoon Shad @pipvav Port (2012-13)
• Industrial shad of 800 X 700 mtr.
• 320 Raft & Pedestal Foundation with Anchor Bolts.
• Other activity like concrete base, paver floor. Hopper foundation for urea bagging machine
• Wagon loading system raft and pedestal foundation and rail fixing with anchor bolts and fish plat
• Strom water drain and dyke wall.
Client: Aegis gas (i) Pvt. Ltd.
Project-3: LPG sphere tank & Liquid storage tank for plant- 1 & 2 (2013-2015) & (2016-18)
• Execution of Sphere tank for LPG gas (circular) capacity of each tank is 13.5 MT.6 nos in P-1 & 6 nos in P-2.
• 48 piles in each Sphere tank and 25.5mtr and diameter 600mm
• Execution of liquid tanks average capacity of each- 1500KL to 10500KL.
• Total no. of pile: 1700 no’s depth of pile 20mtr and 25.5mtr and diameter 600mm.
• Average concrete consumption in one tank 1150cu.m.
Related work and All utility work for oil & gas deport development
Product line and fire line for railway (rack loading facility)
• 900 mtr length and 03 nos of product pipe and 01 nos underground fire line. (Between two railway track)
• 150 nos foundation for this project
Coordination with port and railway for execution as per OISD and Railway codes.
• Fire and Chemical Pump House & pipe rack, Bound wall, Pipe support collection pits.
• Storm water drain around 4.5 km.
• Tanker Filling shad and Drum Shad, Loading Bay & LPG Gantry.
• Culverts and Hume pipe fixing.
• WBM roads around 3.0 km.
• Concrete floor near TLF areas around 2500 sq.m.
• Building renovation and extension.
• Fencing for LPG area.
• Nitrogen tank foundation and floor with barricaded.
Project-2: Oil Storage terminal @ pipvav Port
Client: Vijay tanks & Vassals (I) Pvt. Ltd. And Gulf Petrochem Ltd.(2013-14)
• Oil Storage Tank Foundation for 28 tanks with Different Diameter -14 M., 19 m., 25 m.
• And other miscellaneous work for depot development including admin building. Pipe rack pipe support stair case foundation, loading gantry, floor etc.
MS Office
First Aid
AutoCAD
Total station